| CITY
OF DES MOINES
ENGINEERING DEPARTMENT
| |
YEAR
2004 CONSTRUCTION PROJECTS
INVOLVING MAJOR STREETS |
|
Office of Traffic
and Transportation
Updated:
March 08, 2004
The following
is a list of planned projects for the year 2004 construction season,
which involve closing or restricting traffic along major streets.
Advance notification of each project will also be done individually,
closer to the beginning of project construction:
1.
M.L. King Jr. Parkway Project
- Fleur
Drive near Waterworks Park
Work has begun on the portion of ML King along Fleur Drive near
Waterworks Park, including two new bridges over the Raccoon River,
to connect the north-south and east-west segments of ML King.
Fleur Drive will be reduced to one lane in each direction during
this construction, which is scheduled for completion by mid-summer
of 2005.
- ML
King – 7th to 16th Streets
The paving portion of this project is completed. Landscape work
should be complete by mid-summer.
- ML
King – Ingersoll to Center
The paving portion of this project is completed. Sidewalk construction,
landscape work, alley construction and brick crosswalk construction
should be complete by late summer. Lane closures will be necessary
at times on ML King and Ingersoll.
- Ingersoll
Avenue to Raccoon River
Work will continue on the retaining wall, bridge railing, street
lighting installation and landscaping through the summer.
2.
SW 9th Street and Porter Intersection
- Work on this
intersection safety improvement, which consists of widening of
SW 9th to provide left-turn lanes and new traffic signals, will
resume this spring. Traffic on SW 9th will be reduced to one lane
in each direction during the work, which will restart in April
and be completed by late summer.
3.
SW 9th Street at Yeader Creek Bridge
- Traffic will
be reduced to one lane in each direction during much of this bridge
replacement work, which will begin in late March and be completed
by December.
4.
6th and Euclid Avenue Intersection
- This Highland
Park Streetscape project is scheduled to begin this spring and
be completed by this fall, and will include new streetlights and
reconstructed traffic signals. It is expected that traffic will
be reduced to one lane in each direction during most of the construction
period.
5.
3rd Street Realignment – Iowa Events Center
- 3rd Street
is closed to allow construction of both the new arena and exhibition
hall. The street is expected to be paved and re-open in June.
6.
E 9th Street – Arthur to Hull - Upper Union Park Storm Sewer
– Phase 2
- E 9th Street
will be closed starting in May, during the Upper Union Park Storm
Sewer project. Other local streets in the area may also be closed
during construction, which will not be complete until 2005.
7.
Park Street – 2nd Ave to 7th St
- Construction
of the Birds Run Outlet Sewer project will continue this year.
Installation of this large sewer has required closing of Park
Street in stages between 7th Street and 2nd Avenue. Traffic has
been detoured via Watson Powell Jr. Way.
8.
E University Avenue at 21st St – Dean Lake Storm Sewer
- Construction
of this storm sewer will begin this spring and be complete by
the end of the year. Lane closures on E University Avenue will
be required during the project.
9.
10th Street Reconstruction – Pleasant to Chestnut
- 10th Street
will be closed for the duration of the project. It is currently
a one-way street, northbound, and will be modified to accommodate
two-way traffic. The construction is planned for the summer and
should take 2 to 3 months to complete.
10.
12th Street Reconstruction – Keo to Center
- This work
includes adding a right-turn lane, along Keo Way west of 12th
Street. 12th Street will be widened to accommodate two lanes of
traffic each way. Construction will be staged to maintain two-way
traffic on 12th Street. The work should take about a month.
11.
SE 14th Street & Indianola Ave Turn-Lane & Signal modifications
- This work
includes adding a right-turn lane on southeast bound Indianola
at SE 14th, which will reduce traffic to one lane for that direction
for about a month. Construction of a median on SE 14th, between
Park and Indianola, is also included in this project, which will
take about a week and shouldn’t impact traffic during peak
hours. The construction is planned for the summer and should take
a total of 2 months to complete.
12.
US Hwy 69 & County Line Road Left-Turn Lanes & Traffic Signals
- This project
will provide traffic signals and left-turn lanes for US Hwy 69
at County Line Road. The outside lane will be closed during off-peak
hours for both northbound and southbound traffic. Construction
will begin in early April, with completion by mid-June.
13.
University Ave Bridge over the Des Moines River
- The bridge
will be reduced to one lane in each direction during most of the
construction, which will include removing the existing asphalt
overlay to repair the deck and replacement of the expansion joints
and approach slabs. Work is scheduled to begin in late spring
with completion in November.
14.
E 30th Street Resurfacing – University to Dean
- This work
will impact traffic for a couple of months this fall.
Iowa DOT projects affecting City Streets
1.
63rd Street at I-235
- This interchange
will be reconstructed from July through the summer of 2005. One
lane of traffic in each direction will be maintained on 63rd Street.
2.
42nd Street at I-235
- This interchange
will be reconstructed from March through July. 42nd Street will
be closed in the vicinity of I-235.
3.
35th Street at I-235
- The 35th
Street roadway will be reconstructed. This work will begin after
completion of the 42nd Street interchange and be completed by
December. 35th Street will be closed in the vicinity of I-235.
4.
5th Avenue / 6th Avenue / 7th Street at I-235
- This reconstruction
will begin in July and continue into late summer of 2005. While
the Fifth and Sixth Avenue bridges are being rebuilt, Seventh
Street will be converted to two-way traffic across I-235. Then
while the Seventh Street bridge is being rebuilt, Sixth Street
will be converted to two-way traffic.
5.
E 14th Street / E 15th Street at I-235
- Construction
is scheduled to run from March through November. This work includes
construction of a new bridge for E 14th Street over I-235. To
maintain north/south traffic, E 15th Street will be converted
to two-way traffic between University Avenue and Lyon Street.
|