| CITY
OF DES MOINES
ENGINEERING DEPARTMENT
| |
YEAR
2007 CONSTRUCTION PROJECTS
INVOLVING MAJOR STREETS |
|
Office
of Traffic and Transportation
Updated:
April 13, 2007
The
following is a list of planned projects
for the year 2007 construction season, which
involve closing or restricting traffic along
major streets. Advance notification of each
project will also be done individually,
closer to the beginning of project construction:
-
McKinley Widening at SE 5th
This project consists of an intersection
widening to provide left-turn lanes on
all four approaches. Traffic signals
will also be installed, replacing the
current 4-way stop condition.
Construction should begin this spring
and be completed later in the fall.
-
E 30th and State Realignment
This project will realign the E 30th
Street and State Avenue intersection to
create a more direct connection between
E 30th and E 29th Streets along State
Avenue. Construction should begin this
spring and be completed by August.
-
SW 7th and Indianola Road
Intersection
This project consists of minor
median and lane modifications at this
intersection, along with upgraded
traffic signals, to allow dual eastbound
left-turn lanes. Construction should
begin this summer and be completed in
the fall.
-
Ingersoll Streetscape, from 28th
Street to 29th Street
Lane closures on Ingersoll Avenue
will be needed during various stages of
this project. 28th Street, north of
Ingersoll, may be restricted for storm
sewer construction. Utility relocation
is scheduled to begin in June, with
streetscape work from July to November.
-
SE 6th Street Viaduct over Des Moines
River
Work on this bridge is scheduled for
late summer or early fall of this year.
It’s anticipated that the bridge will
not need to be closed but traffic
restrictions will be necessary.
-
Des Moines River Outfall – Downtown
sewer crossing 2nd Avenue
A large box sewer has been
constructed along the west side of the
Des Moines River. This next stage will
cross 2nd Avenue, north of Grand, and
then along Watson Powell to a connection
in 3rd Street. Construction will be
phased to maintain traffic, with lane
restrictions, while crossing 2nd Avenue.
Watson Powell will be closed from 2nd
Avenue to 3rd Street during that phase
of work. Also, Locust Street, west of
the river bridge, will be closed for
several weeks to place the permanent
street pavement. This project should be
complete by mid-summer.
-
12th Street Storm Sewer, from Cherry
Street to north of Grand Avenue
Construction of this storm sewer
will require the closing of 12th Street
in stages. Also, Walnut Street at 12th
will be closed for up to 40 days.
Closures necessary at Grand Avenue and
at Locust Street will only occur on
weekends. This project is scheduled to
begin in April, with completion late in
the summer.
-
13th and Jefferson Sewer Reroute
This project will construct a
sanitary sewer from 13th Street and
Jefferson Avenue to a connection in
Prospect Park. This will involve
crossing Hickman Road, with traffic
restricted to one lane in each direction
during the work. The project is
scheduled to begin in early fall and be
completed in mid-summer of 2008.
-
SW Area Diversion Facility - WRA
This project is south of the city
limits, but will close R63 (extension of
SW 9th St), a commuter route, for up to
two weeks for construction of the North
River Interceptor sewer.
Street Resurfacing Projects:
Scarification work will not be allowed during
peak hours, 6:00 – 9:00 AM and 3:30
– 7:00 PM. Traffic in both directions
must be maintained at all times. Paving
will take place at night (8:00 PM –
6:00 AM) or during the weekend. The street
may be closed during paving.
-
Hickman Road, 30th St to Merle Hay Rd
-
ML King Jr Pkwy, Hickman Rd to south of
Euclid Ave
-
SW 9th St, Jarvis St to north of Creston
Ave
-
E Grand Ave, Penn Ave to E 14th St
-
SE 6th St, Hillside St to Livingston Ave
-
Hickman Rd, ML King Jr Pkwy to 9th St
-
Easton Blvd, Stewart St to Delaware Ave
-
28th St, School St to Center St
-
E Grand Ave, east of E 18th St to E 20th
Ct
-
SE 5th St, Army Post Rd to McKinley Ave
Iowa DOT projects affecting City Streets:
I-235 work:
-
In 2007, I-235 mainline traffic lanes
will be paved from east of Keo Way to E
6th Street. 3rd Street and 5th Avenue
interchange ramps will be constructed.
This will impact travel routes into and
out of the downtown area. Also, the
eastbound Des Moines River Bridge and
9th Street Bridge over I-235 will be
completed. Please visit the Iowa DOT’s
website (www.I235.com) for information
and updates on this project.
Other IDOT Projects:
-
Euclid Avenue Resurfacing, from 6th
Avenue to ML King Jr Pkwy
-
E 14th / E 15th Street Resurfacing, from
Garfield Ave to the Des Moines River
If
there are any questions concerning these
major street restrictions or closures, please
contact the City of Des Moines Traffic and
Transportation Division at 283-4973.
|