6. Des Moines River Outfall – Downtown sewer crossing
2nd Avenue
A large box sewer has been constructed along the west side of
the Des Moines River. This next stage will cross 2nd Avenue,
north of Grand, and then along Watson Powell to a connection in
3rd Street. Construction will be phased to maintain traffic,
with lane restrictions, while crossing 2nd Avenue. Watson Powell
will be closed from 2nd Avenue to 3rd Street during that phase
of work. Also, Locust Street, west of the river bridge, will be
closed for several weeks to place the permanent street pavement.
This project should be complete by mid-summer.
|