CITY COUNCIL
COMMUNICATION:
00-288
AGENDA:
JUNE 26, 2000
SUBJECT:
RECOMMENDATION FOR PAVING UNPAVED STREETS
TYPE:
RESOLUTION
ORDINANCE
RECEIVE/FILE
SUBMITTED BY:
JOHN P. BELLIZZI
PUBLIC WORKS DIRECTOR
FLOYD BENTZ
CITY ENGINEER
|
REVISED
ITEM ____
OFFICE OF THE CITY MANAGER
CITY OF DES MOINES, IOWA
SYNOPSIS -
The Public Works and Engineering Departments have developed a proposed plan for paving the City's remaining
50 miles of unpaved streets. The majority of unpaved miles appear to be candidates for either permanent intermediate
depth or interim asphalt (10 year design life) pavements. It is recommended that intermediate paving now be performed
under contract through the Engineering Department and be assessed for the following project costs:
· Pavement and curb construction (50 percent assessed)
· Driveway approaches (50 percent assessed)
· Related engineering design and inspection costs (limited to 10 percent of the total construction cost)
The major non-assessable items would include the following:
· Subgrade stabilization using existing roadway surface material
· Storm intakes and sewer construction needed to accommodate street drainage
· Sod replacement
In addition, the 10 percent Default Fund would be eliminated.
The Public Works Department will continue to place non-assessed interim pavements in conjunction with the Neighborhood
Infrastructure Rehabilitation Program and as required in other low density or undeveloped areas where no sanitary
sewer exists.
FISCAL IMPACT -
Funding for the first year of the proposed paving plan is available in the Capital Improvements Program (CIP City-Wide
Paving Account No. CP038 ENG990000 STRO13) in the amount of $810,021, $100,000 from the Public Works Department's
operating budget, and $231,816 in assessments.
RECOMMENDATION -
Direct the city engineer to complete a feasibility study to determine which of the City's unpaved streets are
candidates for intermediate paving and authorize the city engineer to take alternate PCC and ACC bids for the placement
of intermediate depth pavements. Allow the city engineer to proceed with full depth paving where traffic volumes
dictate. Authorize the Public Works Department to proceed with non-assessed interim asphalt pavements (10 year
design life) in low-density residential areas or open areas with development pending and no sanitary sewer available.
BACKGROUND -
On December 5, 1994, by Roll Call No. 94-4615, the City Council authorized the Public Works Department to proceed
with permanent intermediate paving programs and assess only 50 percent of the project costs in order to increase
the number of street surfaces paved within the city of Des Moines. Subsequently, on March 1, 1999, by Roll Call
No. 99-606, the City Council excluded from assessment storm sewer improvements associated with intermediate paving
because of the stormwater utility fee-funded program and storm sewer improvements.
On February 8, 2000, the Public Works Department distributed the attached street pavement report during the course
of the City Council's budget hearings. The report detailed paving alternatives, which included both intermediate
depth pavements and interim pavements. It is recommended that those paving alternatives be adopted by the City
Council.
Current design standards for residential pavement thickness are for alternate bids of 6-inch portland cement concrete
versus 8 inches of asphaltic concrete between concrete curb and gutter. The design calls for these pavements to
be placed upon compacted subgrade, which results in a 50-year design life for the total pavement section. Experience
has taught us that in areas of poor subgrade, such as expansive soils and soils highly susceptible to frost heave,
this pavement section performed below expectations. As a result of our experience, the specifications for the last
eight years have required placing the pavements on a stabilized base. This 6-inch thick base consists of recompacting
the existing roadway materials and using moisture density control for the compaction of the soil below the stabilized
base. Pavements placed on these stabilized bases have performed very well.
The Engineering Department has recently reviewed its residential pavement designs and has determined that 5 inches
of portland cement concrete or 7 inches of asphaltic concrete placed on the stabilized base is structurally equivalent
to the original 6 inches of portland cement concrete or 8 inch asphaltic concrete placed upon only a compacted
subgrade. Based upon our experience with stabilized base, we believe that the recommended design change is superior
to the original pavement design that did not include the stabilized base.
Street storm drainage in the form of intakes and sewers will be designed for both alternatives and suitable outlets
will be established in terms of either existing storm sewers or open drainageways.
Parkings will be restored with grass sod, and driveway approaches will be paved as part of the project to the right-of-way
line.
The street paving program for Year 2000 for intermediate paving includes the following streets:
· Garfield Avenue, from East 32nd to East 33rd Streets
· SW 26th Street, from Stanton to McKinley Avenues
· East 36th Street, from Arthur to East Sheridan Avenues
· SE 9th Street, from East Hillside to East Hartford Avenues
· SW 12th Place, from Army Post Road to the dead end north
Funding for the first year of the proposed paving plan is available in the CIP in the amount of $810,021, $100,000
from the Public Works Department's operating budget, and $231,816 in assessments.
Over the last several years, the Public Works Department's commitment to the Neighborhood Infrastructure Rehabilitation
Program and other unmet maintenance needs has limited the time available to perform permanent intermediate paving
during the construction season. Further, the Public Works Department has initiated the use of interim (10 year
design life) pavements to replace the poorly regarded asphalt stabilization program. Interim pavements have been
shown to reduce overall maintenance costs while increasing customer satisfaction. Approximately 2 miles of interim
pavements will be constructed by the Public Works Department in the Gray's Woods Area during this construction
season, as well as on SE 34th Street from Evergreen Avenue to Watrous Avenue, and Watrous Avenue from SE 34th Street
to the east city limits.
Attachment
|