Date |
May 22, 2006 |
||
|
Agenda Item No. 10 Roll Call No. 06- Communication No. 06-296 Submitted by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Approving and authorizing the execution of Iowa Department of Transportation (IDOT) Project Agreement to upgrade four mid-block pedestrian crossing locations: 1) University Avenue east of 29th Street; 2) University Avenue at 27th Street; 3) University Avenue at 4th Street; and 4) Grand Avenue at East 13th Street.
SYNOPSIS:
Approval of Iowa Department of Transportation (IDOT) Project Agreement No. 2007-TS-003 for Traffic Safety Improvement Program project funding for the purchase and construction of pedestrian crossing enhancements at four locations: 1) University Avenue east of 29th Street; 2) University Avenue at 27th Street; 3) University Avenue at 4th Street; and 4) Grand Avenue at East 13th Street. IDOT funds in the amount of $75,000 are available for the purchase of the equipment. The City’s portion of the project, consisting of the design, inspection, and construction costs, is estimated to be $90,000.
FISCAL IMPACT:
Amount: $165,000
Funding Source: Various funding sources as follows:
ADDITIONAL INFORMATION:
In July of 2005, City Council authorized that an application be submitted to the IDOT for “Midblock Pedestrian Crossing Enhancements”. The IDOT has approved $75,000 for this project. The remaining costs, including design, construction, and project administration, are to be funded by the City. The total City cost is estimated to be $90,000.
Three of these locations will involve installation of push-button activated pedestrian warning signs, similar to the City’s current installation on University Avenue at 26th Street. The fourth location, on University east of 29th Street, will consist of a mid-block pedestrian-actuated traffic signal, along with relocation of the existing Drake parking lot driveway to a point approximately 170 feet east of the new signal location.
PREVIOUS COUNCIL ACTION(S):
Date: July 25, 2005
Roll Call Number: 05-1791
Action: Approving applications to the Iowa Department of Transportation for traffic safety funds to cover a portion of construction costs for the following projects: (Council Communication No. 05-412) Moved by Hensley to adopt. Motion Carried 6-1.
(A) East Army Post Road Widening from South Union to SE 5th Street.
(B) SW 7th and Indianola Road Traffic Signal/Channelization Improvements.
(C) E. 29th and Hubbell Intersection Traffic Signal Upgrading.
(D) 5th, 6th, and 7th at Crocker Street-Traffic Signal Upgrading.
(E) Midblock Pedestrian Crossing Enhancements.
BOARD/COMMISSION ACTION(S): NONE
Date:
Roll Call Number:
Action:
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Normal actions for award of the construction contract for the work.