Council
Communication

Office of the City Manager

 
 

Date

August 7, 2006

 

Agenda Item No.       9

Roll Call No.              06-

Communication No.  06-501

Submitted by:  Jeb E. Brewer, P.E.

City Engineer and William G. Stowe, Assistant City Manager/Public Works/ Engineering

 

AGENDA HEADING:

 

Approving and authorizing the execution of Iowa Department of Transportation (IDOT) Change Order No. 2 to Keo Way Phase 2 Storm Sewer Outlet not to exceed City cost of $124,716.53.

 

SYNOPSIS:

 

City Council approved a preconstruction agreement with IDOT for Keo Way (Birds Run) Phase 2 Storm Sewer related to I-235.  As part of this agreement, change orders exceeding $25,000 in additional City contribution must be approved by the Des Moines City Council.  Change Order No. 2 in the amount not to exceed $374,149.58, City share being $124,716.53, is for boring the sewers underneath the utilities.

 

FISCAL IMPACT:

 

Amount:  $124,716.53

 

Funding Source:  2006-2007 CIP, Page Street-23, I-235 Storm and Sanitary Sewer Improvements, STR197, Storm Sewer Utility Funds.

 

Amount:  $124,716.53

 

Funding Source:  Iowa Department of Transportation State Funds.

 

Amount:  $124,716.52

 

Funding Source:  Qwest Communications

 

 

ADDITIONAL INFORMATION:

 

The City and IDOT entered into a preconstruction agreement where the City will repay IDOT an estimated 57% of the storm sewer cost, 100% for any enhanced storm capacity, and 100% of sanitary sewer cost.  The repayment will begin in FY 2007-08.  Change orders affecting the City’s final cost will be approved by the City.

 

Change Order No. 2 is for the cost to bore 40 lineal feet of 54-inch sanitary sewer with casing and 84 lineal feet of 10 ft. x 5 ft. reinforced concrete box storm (RCB) sewer underneath the Qwest communication utilities.  Various alternatives to construct the 54-inch sanitary sewer and 10 ft. x 5 ft. RCB underneath the utilities were discussed between the City, IDOT, and Qwest.

 

·        The first alternative was to perform open cut construction. IDOT’s consultant had chosen this alternative in the original construction documents, as Qwest indicated that their ducts could be supported over the open trench.  However, Qwest has determined that their ducts at this location do not have structural integrity to allow the contractor to support the duct bank over the open cut sewer construction; therefore, construction is not feasible as originally planned.

 

·        A second alternative was explored to completely replace the Qwest ducts.  Qwest ducts must be reconstructed from access manhole to access manhole, which is approximately 900 feet long from south of Keo Way north to Crocker Street.  Construction of the new duct would require several stages of traffic control across Keo Way, additional construction time, and coordination between the two projects.

 

·        A third alternative was explored to bore the sanitary and storm sewers under the Qwest ducts, which would minimize the disruption to traffic flow on Keo Way, meets the project schedule coordination with IDOT for traffic flow from I-235 this fall, and does not extend construction time.  This option requires additional cost on the sewer contract.  Since this option is beneficial to Qwest as it eliminates their cost to relocate the duct, beneficial to the IDOT in order to keep traffic phasing on schedule, and beneficial to the City in order to minimize downtown access disruptions, all three parties have agreed to share the cost equally and proceed with this option.  The total change order cost is $374,149.58, with the City’s share being $124,716.53.

 

 

PREVIOUS COUNCIL ACTION(S):

 

Date:    May 22, 2006

 

Roll Call Number:  06-977      

 

Action:  Authorizing execution of Iowa Department of Transportation Preconstruction Agreement for Keo Way (Birds Run) Phase 2 Storm Sewer Outlet.  (Council Communication No. 06-294).

 

Date:    August 31, 2000

 

Roll Call Number:  00-3634

 

Action:   Approving Iowa Department of Transportation Predesign Agreement for Interstate 235, from the west City limits to the north City limits.  (Council Communication No. 00-411).

 

 

BOARD/COMMISSION ACTION(S):  NONE

 

Date:

 

Board/Commission Action:      

 

Action:

 

 

ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:  NONE