Date
|
August 7, 2006
|
|
|
|
Agenda
Item No. 8 Roll
Call No. 06- Communication No. 06-502 Submitted by:
Jeb E. Brewer, P.E., City Engineer and Larry Hulse, Community Development Director |
|||||
AGENDA HEADING:
SYNOPSIS:
Recommend
approval of the authorization for
Douglas Hoerr Landscape Architecture, Inc. to proceed with Phase 3 (Design
Development) and Phase 4 (Bidding Phase) of the Professional Services Agreement
Scope of Services for the Ingersoll Avenue Streetscape project. This will authorize the consultant to
proceed with the development of final plans and construction documents for the
pilot project between 28th Street and 31st Street. Construction is anticipated to take place in
the summer and fall of 2007.
FISCAL IMPACT:
Amount:
$123,655
Funding Source: 2006-07 CIP, Page Street-24, STR221,
Ingersoll Streetscape Improvements 28th-31st, G.O. Bonds. This
amount is included in the $238,655 previously approved by Council on October
24, 2005
ADDITIONAL INFORMATION:
On October 24, 2005, the City Council approved the Professional
Services Agreement with Douglas Hoerr
Landscape Architecture, Inc. for the design of the Ingersoll Streetscape
Project for compensation not to exceed $238,655. Their Scope of Services contained all four phases of work, including
phases 3 and 4. Phase 1 (Schematic
Design) has been completed and two schematic design concepts, a base concept
and an enhanced concept, were presented to the public at Des Moines University
on February 28, 2006. Following the
completion of the conceptual design, the Ingersoll Area Association (IAA) began
Phase 2 (Community Fundraising) to raise private donations to match the City’s
contribution towards construction of the streetscape. During this phase, the Consultant researched other possible funding
sources, provided graphics and technical assistance to the IAA as needed. Phase 2 is nearing completion and a
preliminary construction budget has been established based on the funds
received at this time. The current
project budget is as follows:
Estimated
Project Budget
$650,000 City (FY 2005
& FY 2006 CIP)
$150,000 FY 2006 STP-TE
Grant (DM MPO/ IDOT)
$364,875 Private Donations
(includes both received and
pledged amounts)
$1,164,875 Total Budget
($238,655) Consultant Design
Contract
($150,000) Estimated
Consultant Construction Administration
($70,000) Estimated City
Expenses
$706,220 Remaining
Budget for Construction
Based on this
$706,000 budget, the proposed pilot project will be greater than the base
conceptual design ($280,000 estimated cost), but less than the enhanced
conceptual design ($1,840,000). It is
anticipated that the pilot project will include new street curbs, new sidewalks
and drive approaches, some trees and landscape plantings, some street
furnishing, and upgraded street lighting from MidAmerican Energy.
City staff and
IAA representatives met and decided that it is preferable to proceed with
construction of the pilot project in 2007, based on the available funds, rather
than delay the project for a year to try to obtain additional funds. The improvements will be designed with the
ability to add elements to the project as the IAA raises additional private
funds. The plans for the pilot project
will need to be submitted to the Iowa DOT in October of 2006. The final construction budget will include
those donations received or pledged by September 30, 2006.
Phase 3 of the
Scope of Services consists of the development of final plans and construction
documents and the coordination of the Iowa Department of Transportation during
the plan review process. Phase 4 of the
Scope of Services is the bidding phase.
It is anticipated the project will be bid in March or April of 2007. Completion of construction is anticipated by
fall of 2007. The $123,655 cost for
Phase 3 and 4 is included in the total consultant design fee of $238,655
previously approved by Council.
PREVIOUS COUNCIL ACTION(S):
Date:
October 24, 2005
Roll Call Number: 05-2597
Action: Professional Services Agreement with Douglas
Hoerr Landscape Architecture Inc. (Douglas Hoerr, Principal, Chicago, IL) for
the Ingersoll Avenue Streetscape Project, not to exceed $238,655. (Council
Communication No. 05-594)
BOARD/COMMISSION ACTION(S): NONE
Date:
Roll Call Number:
Action:
ANTICIPATED ACTIONS AND FUTURE
COMMITMENTS:
Normal
Council action for administration of construction contracts.