Date
|
March 12, 2007
|
||
|
Agenda
Item No. 15 Roll
Call No. 07- Communication No. 07-131 Submitted by: Jeb E. Brewer, P.E.,
City Engineer |
||||
AGENDA HEADING:
SYNOPSIS:
Recommend authorization to acquire
necessary right-of-way and easements for the above project. This action is required by Iowa law before
the City can initiate the right-of-way acquisition process under eminent
domain.
FISCAL IMPACT:
Amount: $2,500 estimated
for right-of-way acquisition
Funding Source:
2006-07 CIP, Street Improvements, Page 24, Ingersoll Streetscape Improvements
28th – 31st, STR221.
ADDITIONAL INFORMATION:
The Ingersoll
Avenue Streetscape Improvements Project from the 28th Street
intersection to the 31st Street intersection includes planting,
lighting, street trees, street furniture, signage and traffic calming
improvements. The pilot project is an
outcome of a two-year planning effort with the Ingersoll Area Association and
the surrounding neighborhood associations.
This effort culminated in the development of the Ingersoll Avenue
Improvement Plan. The neighborhood has
raised funds for a portion of this project, as well as approved a
Self-Supported Municipal Improvement District (SSMID) for long-term
maintenance.
Several
temporary easements will be needed to reconstruct driveway approaches and several
permanent easements are needed for storm sewer improvements that will be made
in conjunction with this project.
PREVIOUS COUNCIL ACTION(S):
Date: February 12, 2007
Roll Call Numbers:
07-270
Action: Establishing
the Ingersoll Avenue Self-Supported Municipal Improvement District (SSMID), and
providing for the establishment of a capital improvement and operation fund,
and levy of an annual tax. (Council
Communication No. 07-067) Moved by Hensley that this ordinance be
considered and given first vote for passage.
Motion Carried 6-0. Mayor Cownie
declares a conflict of interest and abstains from voting.
Date: February 12, 2007
Roll Call Numbers:
07-271
Action: Final
consideration of ordinance above, (waiver requested by City Manager), requires
6 votes. Moved by Hensley that the rule requiring that an ordinance must be
considered and voted on for passage at two Council meetings prior to the
meeting at which it is to be finally passed be suspended, that the ordinance be
placed upon its final passage and that the ordinance do now pass, #14,628. Motion Carried 6-0. Mayor Cownie declares a conflict of interest
and abstains from voting.
Date: August 7, 2006
Roll Call Number:
06-1554
Action: Authorizing
City Engineer to issue Notice to Proceed to Douglas Hoerr Landscape
Architecture, Inc. for Phase 3 (Design and Development) and Phase 4 (Bidding
Phase) of Professional Services Agreement for the Ingersoll Avenue Streetscape
Project. (Council
Communication No. 06-502) Moved by Vlassis to adopt. Motion Carried 6-1.
Date: October 24, 2005
Roll Call Number:
05-2597
Action: Professional
Services Agreement with Douglas Hoerr Landscape Architecture Inc. (Douglas
Hoerr, Principal, Chicago, IL) for the Ingersoll Avenue Streetscape Project,
not to exceed $238,655. (Council
Communication No. 05-594) Moved by Hensley to adopt. Motion Carried 7-0.
BOARD/COMMISSION ACTION(S):
Date: December 7,
2006
Roll Call Number:
NA
Action:
The Plan and Zoning Commission approved the evaluative report and recommended
approval of the Ingersoll Avenue SSMID.
ANTICIPATED ACTIONS AND FUTURE
COMMITMENTS: NONE