Date
|
May 7, 2007
|
||
|
Agenda Item No. 6A Roll Call No. 07- Communication
No. 07-270 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Ordering construction of the following: Evelyn K. Davis Park Improvements - Receiving bids, (5-22-07), and Setting date of hearing, (6-4-07). (Construction Estimate - $375,430)
SYNOPSIS:
Proceed with construction of the
improvement utilizing the method of financing referenced below and set dates to
receive bids and hold a public hearing as required by Iowa Code. Neighborhood Association and stakeholder
meetings were held in October and November 2006 and April 2007 to gain
consensus on the specific improvements for Evelyn K. Davis Park, which were
approved at the November 14, 2007 King-Irving Neighborhood Association
Executive Board meeting and include: a
new half-court basketball court; a Spacenet Climber; a prefabricated, painted
steel open-air shelter for 40 people with permanently installed picnic tables
and grills; the existing restrooms in the small shelter will be expanded and
remodeled; additional landscaping; and a walking path around the perimeter of
the park.
FISCAL IMPACT:
Amount: $375,430 City Engineer's Estimate
Funding Source: 2007-2008 CIP, Page Park-8, Evelyn K. Davis Park Improvements, PKS168, Various Funding, Being: $130,000 from a Community Attraction and Tourism (CAT) Grant, $100,000 from Polk County, $50,430 from Prairie Meadows, $25,000 from United Way, and $70,000 G.O. Bonds
ADDITIONAL INFORMATION:
The Evelyn K. Davis Park Improvements Project will total
$450,000 in capital improvements in the City of
In addition to the infrastructure components previously
outlined, a second project component, inherent to the desired outcomes of
increased park use and safety, involves additional park management and
operations funding to increase programming and family-oriented activity as well
as a police presence at the park. This
has been funded with $425,000 of donations from private individuals and will be
used over the course of the next three fiscal years for operating expenses
related to increased security staffing by the Police Department and programming
staffing by the Park and Recreation Department.
The Engineering Department has
prepared plans, specifications, form of contract documents, and City Engineer’s
estimate for the construction of the Evelyn K. Davis Park Improvements,
11-2007-014. The improvement includes
construction of a restroom addition, Spacenet Climber, shelter, basketball
court, sidewalk, earthwork, and plantings, all in accordance with the contract
documents including Plan File Nos. 473-032/045 at Evelyn K. Davis Park,
The estimated construction cost is $375,430. The proposed plans, specifications, and form of contract documents are available for public inspection in the City Engineer's Office.
PREVIOUS COUNCIL ACTION(S):
Date: March 12, 2007
Roll Call Number: 07-499
Action: Community
Attraction and Tourism (CAT) Program Agreement with Vision Iowa Board for
acceptance of a $130,000 award for the Evelyn K. Davis Park Improvements
Project. (Council
Communication No. 07-145) Moved by Mahaffey to approve. Motion Carried 6-1.
Date: September 25, 2006
Roll Call Number: 06-1931
Action: Items regarding Evelyn K. Davis Park Improvements and Programs: (A) Authorization to submit Community Attraction and Tourism (CAT) Grant Application and to reappropriate $50,000 of FY 2006-07 Park and Recreation Department CIP Budget. Moved by Vlassis to adopt. Motion Carried 6-0.
Date: September 25, 2006
Roll Call Number: 06-1932
Action: Items regarding Evelyn K. Davis Park Improvements and Programs: (B) Acceptance of donations to fund the improvements. (Council Communication No. 06-623) Moved by Vlassis to adopt. Motion Carried 6-0.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Anticipated actions include public hearing, receive and file bids, designate lowest bidder, and approve contract and bond; also partial payments to the contractor and final acceptance of work.