Date
|
October 22, 2007
|
||
|
Agenda Item No. 6 Roll Call No. 07- Communication
No. 07-638 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Ordering construction of the
following:
SYNOPSIS:
Recommend the City Council proceed with construction of the improvement and set dates to receive bids and hold a public hearing, as required by Iowa Code, utilizing the method of financing referenced below.
This project provides for the upgrading of the existing
traffic signals at the intersection of
FISCAL IMPACT:
Amount: $119,000 (City Engineer's Estimate)
Funding Source: 2007-2008 CIP, Page TFC-5, City-wide Signals, Channelization, and School Crossing Protection Program, TFC091, Being: Iowa DOT Traffic Safety Funds for 100% construction cost only with $140,000 maximum
ADDITIONAL INFORMATION:
The Engineering Department has
prepared plans, specifications, form of contract documents, and City Engineer’s
estimate for the construction of the
The estimated construction cost is $119,000. The proposed plans, specifications, and form of contract documents are available for public inspection in the City Engineer's Office.
PREVIOUS COUNCIL ACTION(S):
Date: July 24, 2006
Roll Call Number: 06-1428
Action: Approving execution of Iowa Department of
Transportation Agreement for
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Anticipated actions include public hearing, receive and file bids, designate lowest bidder, and approve contract and bond; also partial payments to the contractor and final acceptance of work.