Date
|
November 19, 2007
|
||
|
Agenda
Item No. 64 Roll
Call No. 07- Communication No. 07-680 Submitted by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Approving Project Cooperation Agreement between the
City and the Department of the Army for construction of Phase I of the
Principal Riverwalk and approving agreement among the City and the Principal
Life Insurance Company and the Des Moines River Front Development Authority for
responsibility of Non-Federal Sponsor financial obligations and work related to
the Principal Riverwalk.
SYNOPSIS:
Recommend
approval of the Project Cooperation
Agreement (PCA) with the Department of the Army and the related agreement with
Principal Life Insurance Company, (Barry Griswell, Chairman and CEO, 711
High Street Des Moines, Iowa), and the
Des Moines River Front Development Authority (RDA), (Mary O’Keefe,
President, 711 High Street, Des Moines, Iowa), to proceed with Corps of Engineer construction of the Principal
Riverwalk. The PCA makes the City
responsible for 50% of the project costs.
Eligible work in-kind will be reviewed by the Corps of Engineers and
credited towards the City’s share. The
agreement with Principal and RDA places financial responsibility with the RDA
and Principal should the Corps of Engineers determine that a cash contribution
is necessary per the terms of the PCA.
FISCAL IMPACT:
Amount: $19,427,100
(City costs are limited to $3,035,000)
Funding
Source: The non-Federal cost
share for the project is estimated at $19,427,100. This includes the following: $11,594,500 of work-in-kind credit for
eligible design and construction costs incurred, $3,029,500 credit for the
value of land incorporated into the project, and an estimated $4,803,100 for
required cash contribution. City costs
are limited to $3,035,000 for the Principal Riverwalk project. To date, all City funds have been spent on completed work or
committed. These funds are included in
the Fiscal Year 2007-08 Capital Improvement Program, Riverwalk, PKS162
CP040PKS990000, Page Park Improvements – 23, Tax Increment.
The
current Corps of Engineer’s cost estimate of $37,259,700, includes the
non-Federal cost share of $19,427,100 and Federal funding from the
ADDITIONAL INFORMATION:
The PCA
includes the responsibilities of the Corps of Engineers and the City for
financial obligations and work related to the project. In turn, the agreement with Principal and the
RDA assigns responsibilities for funding and participating in the project. The RDA and Principal have executed the
agreement.
The Corps of
Engineers defined project is $37,259,700.
Portions of the defined project have already been completed, including
design work and construction of the
The Corps of
Engineers defined project cost estimate does not include all of the Principal
Riverwalk. The following items are not
included in the Corps of Engineer’s defined project estimate: Brenton Skating Plaza, Hansen Company Triangle,
donated artwork, or the full value of projects constructed with other Federal
funds, such as the Riverpoint Trail,
The design of remaining Riverwalk projects is being finalized. Construction of the remaining Riverwalk
project components is dependant on receiving additional funding. Should
PREVIOUS COUNCIL ACTION(S):
Date:
July 23, 2007
Roll Call
Number: 07-1407
Action: Issuance
of Self-Certification of Financial Capability to the Corps of Engineers for the
Principal Riverwalk Project. (Council
Communication No. 07-448) Moved by Vlassis to adopt. Motion Carried 7-0.
Date: October 24, 2005
Roll
Call Number: 05-2600
Action: Vision
Iowa Program Grant Award Agreement for the construction of the Rediscovering
the Rivers Project including the Principal Riverwalk and Meredith Riverpoint
Trail. (Council
Communication No. 05-596) Moved by Hensley to adopt. Motion Carried 7-0.
Date: April 25, 2005
Roll
Call Number: 05-1062
Action: Intergovernmental
28E Agreement with the Des Moines Riverfront Development Authority, for
planning, constructing and maintaining riverfront improvements in the Downtown
area. (Council
Communication No. 05-230) Moved by Hensley to adopt. Motion Carried 7-0.
Date: March 22, 2004
Roll
Call Number: 04-599
Action: Execution
of a Design Agreement with the Department of the Army for design of the
Principal Riverwalk and related agreement with Principal Life Insurance
Company. (Council
Communication No. 04-153). Moved by Hensley to adopt. Motion Carried 6-1. Nays: Brooks.
Date: August 25, 2003
Roll
Call Number: 03-2011
Action: Regarding
the Principal Riverwalk and Riverfront use items (including letter of
assurance to the Corps of Engineers).
(Council
Communication No. 03-422). Moved by Vlassis to
adopt. Motion Carried 6-1. Absent: McPherson.
Date: March 24,
2003
Roll Call Number: 03-684
Action: Approved Phase I of the Principal
Riverwalk Concept Plan and directed the City Manager to undertake several
actions toward the implementation of Phase I of the Principal Riverwalk Concept
Plan. (Council
Communication No. 03-132). Moved by Vlassis to adopt. Motion Carried 7-0.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Acceptance
of completed project components.