Date
|
December 3, 2007
|
|
|
Agenda
Item No. 7 Roll
Call No. 07- Communication No. 07-718 Submitted by: Jeb E. Brewer,
|
||||
AGENDA
HEADING:
Approving and
authorizing the execution of Iowa Department of Transportation (IDOT) Change
Order No. 22 to Keo Way Phase 2 Storm Sewer Outlet not to exceed City cost of
$35,473.04.
SYNOPSIS:
Recommend approval
of Change Order No. 22 as prepared by IDOT in the amount not to exceed
$35,473.04, for the cost to extend a 6-inch sanitary sewer service 200 feet and
remove and replace part of a parking lot.
FISCAL
IMPACT:
Amount:
$35,473.04
Funding
Source: 2007-2008 CIP, Page Street-23, I-235 Storm
and Sanitary Sewer Improvements, STR197, Storm Water Utility Funds.
ADDITIONAL
INFORMATION:
On May 22, 2006,
under Roll Call No. 06-977, the City Council approved a preconstruction
agreement with Iowa DOT for
Change
Order No. 22 is for additional cost to extend 200 linear feet of 6-inch DI pipe
and install one 48‑inch manhole along the Owen Crist parking lot at
PREVIOUS
COUNCIL ACTION(S):
Date:
July 23, 2007
Roll Call
Number: 07-1385
Action: Approving
and authorizing execution of Iowa Department of Transportation (IDOT) Change
Order No. 18 to Keo Way Phase 2 Storm Sewer Outlet, $48,773. (Council
Communication No. 07-447) Moved by Vlassis to adopt. Motion Carried 7-0.
Date:
April 9, 2007
Roll Call
Number: 07-627
Action: Approving
execution of Iowa Department of Transportation (IDOT) Change Order No. 9 to Keo
Way Phase 2 Storm Sewer Outlet, not to exceed $138,275.75. (Council
Communication No. 07-186) Moved
by Vlassis to adopt. Motion Carried 7-0.
Date:
December 4, 2006
Roll Call
Number: 06-2352
Action: Approving
Change Order No. 7 with Iowa Department of Transportation for Keo Way Phase 2
Storm Sewer Outlet, not to exceed City cost of $138,831.06. (Council
Communication No. 06-752) Moved by Vlassis to adopt. Motion Carried 6-0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED