AGENDA HEADING:
Hearing on American Discovery Trail Wetlands Mitigation: Resolution approving plans, specifications, form of contract documents, engineer’s estimate, receive and file bids, and designating lowest responsible bidder as C.A.C., Inc., Chris Christensen, Owner, $126,370.
SYNOPSIS:
Recommend to hold a public
hearing to allow for public input on the American Discovery Trail Wetlands
Mitigation and to take the necessary actions as required by Iowa Code to
authorize a contract for construction of the proposed project. The construction of Segment 3 of the American
Discovery Trail along the east side of
FISCAL IMPACT:
Amount: $126,370 Construction Contract ($215,000 City Engineer's Estimate)
Funding Source: 2007-2008 CIP,
ADDITIONAL INFORMATION:
The 0.9-mile alignment of Segment 3 of the Walnut Creek
Connection of the American Discovery Trail (ADT) will be a ten-foot wide
asphalt recreational trail along the east side of Walnut Creek that will
connect other segments of the ADT between North Valley Drive and the Bill Riley
Trail in Ashworth Park.
Section 404 of the Clean Water Act requires the City of
On November 5, 2007, by Roll
Call No. 07-2110, the City Council received and filed plans, specifications,
form of contract documents, and City Engineer's estimate for the construction
of the American Discovery Trail Wetlands Mitigation. Before the City Council can enter into a
contract, it must hold a public hearing and approve the proposed plans,
specifications, and form of contract documents and engineer's estimate for the
construction of the American Discovery Trail Wetlands Mitigation, 11-2008-002. The improvement includes a twenty-one acre
wetland construction project which includes earthwork, seeding, shrubs, trees
and other related items in the vicinity of
Sealed bids for the improvement were submitted by the following bidders:
C.A.C., Inc.,
Corell Contractor, Inc.,
Peterson Contractors Inc.,
Applied Ecological Services,
Synergy Contracting LLC,
Spring
The bids were received and opened at a public meeting presided over by the City Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray Drive, Des Moines, Iowa at 11:00 a.m. on November 20, 2007.
The City Engineer has determined
that the lowest responsive, responsible bid for the construction of the improvement
was submitted by C.A.C., Inc., Chris Christensen, Owner,
PREVIOUS COUNCIL ACTION(S):
Date: November 5, 2007
Roll Call Number: 07-2110
Action: Ordering construction of the following: American Discovery Trail Wetlands Mitigation – Receiving of bids, (11-20-07), and Setting date of hearing, (12-3-07). (Construction Estimate - $215,000). (Council Communication No. 07-667) Moved by Kiernan to adopt. Motion Carried 7-0.
Date: October 22, 2007
Roll Call Number: 07-2084
Action: Intergovernmental
28E Agreement with
Date: June 18, 2007
Roll Call Number: 07-1152
Action: Establishing
Fair Market Value for a permanent easement for wetlands mitigation located in
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Partial payments to the contractor and final acceptance of work.