Hearing on Police Station emergency generator: Resolution approving plans, specifications, form of contract documents, engineer’s estimate, receive and file bids, and designating lowest responsible bidder as Stroh Corporation, (Patrick J. Miller, President/CEO), $441,000.
SYNOPSIS:
This is a public hearing to allow for public input on the Police Station emergency generator and take the necessary actions as required by Iowa Code to authorize a contract for construction of the proposed project. The existing emergency generator has been in service for a number of years, and recently has experienced some mechanical problems. The emergency generator needs to be replaced to ensure continued operation of public safety functions during power outages.
FISCAL IMPACT:
Amount: $441,000 Construction Contract ($650,000 City Engineer's Estimate)
Funding Source: 2007-2008 CIP, Page Building-18, Police Station Remodeling, BLD062, G. O. Bonds
ADDITIONAL INFORMATION:
The existing Police Station emergency generator has been in service for a
number of years and has recently experienced some mechanical problems. The emergency generator only provides about
25% of the total electrical power needed to operate the building. It provides emergency power for the
This project would replace the existing emergency generator with a larger
unit sized to back up the entire building facility. Since this will be a larger generator,
numerous modifications to the building are required. The new generator will need to be located
outside the building inside a weatherproof enclosure. Transfer switches will need to be added and
the electrical distribution system will need to be reworked to accommodate the
emergency load transfer equipment.
Modifications to existing mechanical/storage rooms will be required to
accommodate the new electrical equipment.
The existing diesel fuel tank will be able to be reused to serve the new
generator, but a new fuel delivery system will need to be designed.
On November 5, 2007, under Roll
Call No. 07-2111, the City Council received and filed plans, specifications,
form of contract documents, and City Engineer's estimate for the construction
of the Police Station Emergency Generator.
Before the City Council can enter into a contract, it must hold a public
hearing and approve the proposed plans, specifications, and form of contract
documents and engineer's estimate for the construction of the Police Station
Emergency Generator, 04-2007-015. The
improvement includes replacement of the existing emergency generator and main
electrical distribution panel in the Police Station at
Sealed bids for said improvement were submitted by the following bidders:
Stroh Corporation,
Biermann's University Electric
Company, Inc.,
The Waldinger Corporation,
Nikkel and Associates, Inc.,
Schroeder Companies, Inc.,
The bids were received and opened at a public meeting presided over by the City Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray Drive, Des Moines, Iowa at 11:00 a.m. on December 4, 2007.
The City Engineer has determined
that the lowest responsive, responsible bid for the construction of said
improvement was submitted by Stroh Corporation, Patrick J. Miller,
President/CEO,
PREVIOUS COUNCIL ACTION(S):
Date: November 5, 2007
Roll Call Number: 07-2111
Action: Ordering construction of the following: (C) Police Station Emergency Generator – Receiving of bids, (12-4-07), and Setting date of hearing, (12-17-07). (Construction Estimate - $650,000). (Council Communication No. 07-665) Moved by Kiernan to adopt. Motion Carried 7-0.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Partial payments to the contractor and final acceptance of work.