Date
|
January 7, 2008
|
||
|
Agenda
Item No. 8 Roll
Call No. 08- Communication No. 08-013 Submitted by: William G. Stowe, |
||||
AGENDA HEADING:
Approving Supplemental
Agreement No. 5 to the I-235 Birds Run Outlet Storm Sewer Professional Services
Agreement with Veenstra & Kimm, Inc., to perform design modifications and construction
phase services for the Ingersoll Run Outlet Storm Sewer, not to exceed $455,605.22
SYNOPSIS:
Approval of Supplemental Agreement No. 5
to the Professional Services Agreement with Veenstra & Kimm, Inc., H. R.
Veenstra Jr., President,
FISCAL IMPACT:
Amount:
$455,605.22
Funding Source: $250,582.87 – City of Des Moines portion from
the 2007-2008 CIP, Page Street-23, I-235 Storm and Sanitary Sewer Improvements,
STR197 (Loan to be paid back to the Iowa Department of Transportation in 2008,
2009, and 2010); and $205,022.35 from the Iowa Department of Transportation.
ADDITIONAL INFORMATION:
On August 31,
2000, by Roll Call 00-3634, the City Council approved a pre-design agreement
(Agreement No. 2001-P-028) with Iowa Department of Transportation (IDOT) for
Interstate 235 (I-235) from the west city limits to the north city limits. The pre-design agreement with IDOT identified
three storm sewer outlet projects that the City and IDOT are jointly
responsible for, including sharing of funding responsibilities. The three projects are identified as Birds
Run,
This supplement
will be the fifth supplement to the Birds Run Professional Services Agreement. The original agreement and Supplemental
Agreements 1, 3 and 4 were for Birds Run storm design, sanitary design and
construction phase services.
Supplemental Agreements 2 and 5 are for the Ingersoll Run design and
construction phase services. The total cost, including the proposed
supplemental agreement, is not to exceed $2,460,982.22. The total construction cost for the Birds Run
and Ingersoll Run projects is estimated at approximately $20 million.
The I-235 Ingersoll
Run Outlet Storm Sewer project is located along High Street from
These
improvements are necessary as part of a program to meet Iowa Department of
Natural Resources (IDNR) requirements for combined sewer overflow (CSO)
abatement and storm and sanitary separation through implementation of a
long-term control plan which will reduce localized sanitary sewer backups. The City of Des Moines is also taking this
opportunity to construct additional capacity in the I-235 Ingersoll Run Outlet
Storm Sewer, which will become the backbone of the storm sewer system needed to
separate the Ingersoll combined sewer in the future as well as help to address
the chronic flooding problems in the Ingersoll Run Subsystem. Future combined sewer separation projects
will be driven by implementation of the long-term control plan approved by the
IDNR and should provide additional flooding relief within the Ingersoll Run
Subsystem.
The additional
design work included in Supplemental Agreement No. 5 is to connect storm sewers
to
Veenstra &
Kimm, Inc. designed the Ingersoll Run Storm Sewer project from 22nd
and High Street to 34th and
Staff has negotiated a Professional
Services Supplemental Agreement with Veenstra
and Kimm Inc., for a cost plus fixed fee not to exceed $421,474.22, to
provide construction phase services for the I-235 Ingersoll Run Outlet Storm
Sewer and $34,131 to provide design modifications to the final plans for Phase
2 of the Ingersoll Run Outlet Storm Sewer.
PREVIOUS COUNCIL ACTION(S):
Date:
March 10, 2003
Roll Call Number: 03-473
Action: Approving the following Supplemental
Agreements with Veenstra & Kimm, Inc. in conjunction with the I-235 Birds
Run Outlet Storm Sewer: Supplemental No.
2 to perform design phase services for the I-235 Ingersoll Run Outlet along
High Street from
Date:
September 24, 2001
Roll Call Number: 01-2847
Action: Approving Professional Services Agreement
with Veenstra & Kimm, Inc. for design and right-of-way acquisition services
for the I-235 Birds Run Outlet Storm Sewer - Not to exceed $374,087. (Council
Communication No. 01-491) Moved by Vlassis to adopt. Motion Carried 7-0.
Date:
August 31, 2000
Roll Call Number: 00-3634
Action:
Approving Iowa Department of Transportation Predesign Agreement for
Interstate 235, from the west City limits to the north City limits. (Council
Communication No. 00-411). Moved by McPherson to adopt. Motion Carried
4-2-1. Nays: Brooks and Vlassis. Absent: Flagg.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE
COMMITMENTS:
Normal
Council actions on professional services agreements and IDOT construction
contracts.