No. 08-069 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Hearing on Gray's Lake Terrace
Building Shade Structure: Resolution
approving plans, specifications, form of contract documents, engineer’s
estimate, receive and file bids, and designating lowest responsible bidder as
Venter Spooner, Inc., Daniel Venter, President,
SYNOPSIS:
This is a public hearing to
allow for public input on the Gray's Lake Terrace Building Shade Structure and to
take the necessary actions as required by the Iowa Code to authorize a contract
for construction of the proposed project.
The Gray's
FISCAL IMPACT:
Amount: $107,300 Construction Contract ($110,000 City Engineer's Estimate)
Funding Source: 2007-2008 CIP, Page Park-10, Gray's Lake Park Improvements, PKS140, Various Funding, Being: $70,000 in private contributions from the Gray's Lake/Meredith Trail Advisory Group and $37,300 in G. O. Bonds
ADDITIONAL INFORMATION:
Since opening in 2000, the southwest corner of
The
Gray’s
On January 7, 2008, under Roll Call No. 08-017, the City Council received and filed plans, specifications, form of contract documents, and City Engineer's estimate for the construction of the Gray's Lake Terrace Building Shade Structure. Before the City Council can enter into a contract, it must hold a public hearing and approve the proposed plans, specifications, and form of contract documents and engineer's estimate for the construction of the Gray's Lake Terrace Building Shade Structure, 11-2008-003. The improvement includes construction of a shade structure including steel fabrication and erection, fabrication and installation of a stainless steel cable trellis system, provide and install shade fabric, painting and site restoration all in accordance with the contract documents including Plan File Nos. 475-115/121 at Gray’s Lake Park, 2101 Fleur Drive, Des Moines, Iowa.
Sealed bids for said improvement were submitted by the following bidders:
The bids were received and opened at a public meeting presided over by the City Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray Drive, Des Moines, Iowa at 11:00 a.m. on January 29, 2008.
The City Engineer has determined that the lowest responsive, responsible bid for the construction of said improvement was submitted by Venter Spooner, Inc. in the amount of $107,300, and said bid should be accepted. The Finance Director has determined that funds are available for said improvement as stated above.
PREVIOUS COUNCIL ACTION(S):
Date: January 7, 2008
Roll Call Number: 08-017
Action: Ordering
construction of the following: Gray’s
Lake Terrace Building Shade Structure – Receiving of bids, (1-29-08), and
Setting date of hearing, (2-11-08).
(Construction Estimate - $110,000).
(Council
Communication No. 08-015)
Moved by Vlassis to adopt. Motion
Carried 7-0.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Partial payments to the contractor and final acceptance of work.