Date
|
February 11, 2008
|
||
|
Agenda
Item No. 43 Roll
Call No. 08- Communication No. 08-072 Submitted by:
Richard A. Clark, City Manager |
||||
AGENDA HEADING:
Report
from City Manager in response to request from Ted Grob, Savannah Homes,
SYNOPSIS:
At the August
20, 2007 City Council meeting, Council requested follow-up on issues that were
presented regarding the rezoning and development of property at 5100 NE 38th
Street (Douglas Avenue). Staff evaluated the developer’s requests to reduce the
cost of development in
FISCAL IMPACT: NONE
ADDITIONAL INFORMATION:
The following are potential cost savings items
identified by Ted Grob of Savannah Homes regarding the proposed Silver Leaf PUD
at
1. Reduce the east/
Staff believes that the request is acceptable.
2. Eliminate Alleys.
This request was eliminated from consideration by Ted Grob since any lot
without access on an alley must have a garage.
3. Reduce street lights from 35 to 30 (potential
savings $10,000).
This refers to the total number of street lights in the development. Street
light configuration in a subdivision is a collaborative effort involving the
developer's designer, MidAmerican Energy, and City Traffic Engineering. A proposal must be submitted to Traffic for
approval in accordance with set standards. There is no way at this time to tell
how many street lights will be required, since no proposal has been submitted.
4. Allow PVC (plastic) pipe to be used for storm sewer
rather than CIP(cast iron) pipe (potential savings $45,360).
This refers to footing drain storm sewer service
stubs from the public storm sewer system to each lot that will have a basement
in the dwelling. It is a Plumbing
Inspection issue. PVC pipe is allowed as
long as a minimum 48 inches of cover can be maintained over the top of the
pipe. CIP is required within the frost zone.
The developer’s engineer should be able to design the system deep enough
to allow the PVC pipe. Any more discussion of this matter should be with the
Permit and
5. Allow Ecotech to tap each water service
(potential savings of $9,400).
This is Des
Moines Water Works issue that is not under the City Council’s purview.
6. Allow the developer to conduct their own certified
inspections
(potential savings$ 21,420).
This refers to inspection of public improvements
constructed under a Council-approved private construction contract. This has
not been done for any subdivision plats in the past. If allowed to occur,
the scope of services must equal or exceed that of services provided by City
staff and include a Professional Engineer’s certification. The City
staff believes that if the developer is comparing equal services, the cost
difference is very small. In addition, this will be our first narrow
street with a "drivable" sidewalk. Since we are already
allowing differences to the street standards, this project must be
inspected by City staff in order to make sure the proposed changes are
correctly installed. Because of this allowance, City staff does not consider
this request acceptable.
7. Allow cleanouts vs. manholes at the terminus of
sanitary sewers (potential savings $14,000).
This refers to dead end sanitary sewer situations. Manholes must be used at
permanent dead end sanitary sewers. We can allow a cleanout instead of a
manhole in a temporary dead end sanitary sewer situation when future upstream
development would extend the sewer at the same slope and direction. The maximum
distance between the cleanout and the next downstream manhole should
be 100 feet.
8. Allow 500' manhole separation vs.
400' (potential savings $16,500).
The City must follow SUDAS requirements which only allows the 500' spacing for
24-inch or larger diameter sanitary sewers. This would not met the
requirements.
In
addition, Mr. Grob has requested the following assurances.
1. No requirement for sidewalk along
We cannot assure this at this time. Traffic Engineering and Planning
staff currently believe there is a need for sidewalk on the north side of
2. Allow 20' street loop streets with integrated 6'
sidewalk (recycled aggregate sub-base).
The design was previously agreed to by staff.
3. No tree ordinance requirements other than
townparks including construction of detention areas.
The PUD was approved with a condition that a tree survey and protection plan be
submitted with any preliminary plat.
Mitigation would be evaluated at the time of platting. The PUD was also approved with a condition
that overstory trees be planted at 50’ spacing along
4. No requirement for street lights along
Staff believes that the request is acceptable.
5. No
requirement for turn lanes on
Staff believes that the request is
acceptable.
6. Sanitary
sewer allowed being located in townparks vs. streets.
Staff believes that the request is acceptable.
7. Request
that project be “grandfathered” from recently approved ordinance requiring
developer to retain 1 1/4" rainfall on site.
Staff believes that the request is acceptable. However, the developer must attempt to improve
water quality post construction, which is the intent of the new ordinance.
8. Allow
driveway versus turnaround at the end of north /
The north end of the north/south street must be provided with a temporary turn-around
mirroring one of the Fire Department's approved configurations - not
necessarily the cul-de-sac version. No temporary turnaround is required at
the west end of the east /
9. Sanitary Sewer Connection Fee paid with
first occupancy permit rather than at the time of plat approval.
The sanitary sewer connection fee must be paid prior
to final plat approval by Council. Typically developers construct sanitary
sewers upon preliminary plat and public improvement construction plan approval
in order to avoid the cost of providing a subdivision bond for the sewers.
Phased public improvement construction and final platting are
also common. We are able to phase fees, based on the final plat service
areas, by presenting a proposal to Council for approval. This would allow the
developer to delay fee payment until just before the issuance of the first
building permit in the final plat, but not until occupancy.
If the developer would rather
provide a subdivision bond for the required public improvements prior to final
plat approval, and construct the sewers within a year of that approval,
building permits could be issued after the plat is recorded, but no occupancy
certificates could be issued until all public improvements in the ground have
been accepted by Council. In this scenario, the connection fee must be paid
prior to Council acceptance of the "in the ground" public sanitary
sewers.
10. Building Department approves house plans now.
The City currently has a stock plan approval program. The developer should contact
the Permit and
11. All other P&Z conditions still valid.
The developer must comply with all conditions that were approved by the City
Council pursuant to Roll Call 07-1663 on August 20, 2007. Any changes to these conditions are subject to
a re-hearing by the City Council. Staff
believes that review by the Plan and Zoning Commission would be necessary.
PREVIOUS COUNCIL ACTION(S):
Date: January 7, 2008
Roll Call Number: 08-065.
Action: From
Ted Grob, Savannah Homes, 800 50th Street, WDM, to speak regarding
Silver Leaf PUD, 5100 NE 38th Avenue. Moved by Mahaffey to receive
and file comments; refer to the City Manager to work with Mr. Grob and report
back to Council at the January 28, 2008 Council Meeting. Motion Carried 7-0.
Date: August 20, 2007
Roll Call Numbers: 07-1662
Action: Approval
of amendment to the 2020 Community
Character Plan Land Map, request for PUD zoning and Silverleaf PUD Conceptual
Plan subject to conditions. Hearing
on rezoning of the property from “A-1” (Agricultural) to “PUD” (Planned Unit
Development) to develop approx. 37 acres of agricultural land for 121
single-family residential lots and 38 bi-attached residential units. Moved by Mahaffey to adopt and approve the
rezoning and Conceptual Plan, subject to final passage of the rezoning
ordinance; item #10 – Street width—design must be acceptable to the City
Manager and Fire Chief. City Manager will review all issues raised.
Motion Carried 6-1.
Date: August 20, 2007
Roll Call Numbers: 07-1663
through 07-1665.
Action: Hearing
on rezoning of the property from “A-1” (Agricultural) to “PUD” (Planned Unit
Development) to develop approx. 37 acres of agricultural land for 121
single-family residential lots and 38 bi-attached residential units. Moved by Mahaffey to adopt and approve the
rezoning and Conceptual Plan, subject to final passage of the rezoning
ordinance; item #10 – Street width—design must be acceptable to the City
Manager and Fire Chief. City Manager will review all issues raised.
Motion Carried 6-1.
Date: August 6, 2007.
Roll Call Number: 07-1516
Action: On
request from Savanah Homes, Inc. to rezone property in the vicinity of 5100 NE
38th Avenue, from “A-1” (Agricultural) to “PUD” (Planned Unit
Development) and approve a PUD Conceptual Plan for “Silver Leaf”, to include
development of approximately 37 acres of agricultural land for 121
single-family residential lots and 38 bi-attached residential units, (8-20-07).
Moved by Vlassis to adopt.
Motion Carried 7-0.
BOARD/COMMISSION ACTION(S):
Date: July 19, 2007.
Roll Call Number: N/A.
Action: Recommended
approval of the request to designate the subject property as Low Density
Residential and Low-Medium Density Residential on 2020 Community Character Plan
Land Use Map by a vote of 8-1.
Recommended approval of the request for PUD zoning by a vote of 8-1. Recommended approval of the Silverleaf PUD
Concept Plan, with conditions, by a vote of 8-1.
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS: NONE