Date
|
February 25, 2008
|
||
|
Agenda
Item No. 8 Roll
Call No. 08- Communication No. 08-084 Submitted by: William G. Stowe, Assistant City Manager/Public
Works/Engineering & Jeb E. Brewer, P.E., City Engineer |
||||
AGENDA HEADING:
Approving Agreement with MidAmerican Energy for the
installation of underground electrical lines for Dean’s
SYNOPSIS:
Recommend
approval of proposal from MidAmerican Energy to provide the permanent
installation of underground electrical lines for the Dean’s Lake Pump Station,
located south of
FISCAL IMPACT:
Amount:
The total cost for underground electrical installation is $41,736.61
Funding
Source: 2007-2008 CIP, Storm Water Improvements, Page 8,
Dean’s Lake Pump Station Improvements, STE080.
ADDITIONAL INFORMATION:
On October 22, 2007, under Roll Call Number 07-2072, the City Council
awarded a contract to Herberger Construction Co., Inc., Dean Herberger, President,
PREVIOUS COUNCIL ACTION(S):
Date: October 22, 2007
Roll Call Number: 07-2072
Action: Public Hearing, approving plans,
specifications, form of contract documents and engineer’s estimate on Dean’s
Lake Storm Water Pump Station. Council
Communication No. 07-639). Moved by
Meyer to adopt. Motion carried 7-0.
Date: February 26, 2007
Roll Call Number: 07-323
Action: Design and Construction Phase Services for
Dean’s Lake Pump Station Improvements. $520,000.
(Council Communication No. 07-115). Moved by Hensley to adopt. Motion carried 6-1.
Date: October 9, 2006
Roll Call Number: 06-1953
Action: Approving issuance of Request for Proposal on
design and construction phase services for Dean’s Lake Pump Station
Improvements. (Council Communication No.
06-629). Moved by Vlassis to adopt. Motion carried 6-0
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED ACTIONS AND
FUTURE COMMITMENTS:
Final
acceptance of agreement and payment.