Council
Communication
Office of the
City Manager
|
|
|
Date
|
February 25, 2008
|
|
Agenda Item No. 6B
Roll Call No. 08-
Communication
No. 08-086
Submitted
by: Jeb E. Brewer, P.E.
City Engineer
|
AGENDA HEADING:
Ordering construction of the following: Ingersoll Run Storm Sewer - 34th Street to
35th Street - Receiving bids, (3-11-08), and Setting date of hearing,
(3-24-08). (Construction Estimate -
$748,641).
SYNOPSIS:
Recommend the City Council
proceed with construction of the improvement and set dates to receive bids and
hold a public hearing, as required by Iowa Code, utilizing the method of
financing referenced below. This project
provides for the construction of a 6’ x 6’ reinforced concrete box storm sewer
across the Dahl’s Foods Store property at 35th Street and Ingersoll Avenue. Staff has worked with Dahl’s to coordinate
construction of the sewer in three phases to minimize disruption, coordinate
with their parking lot construction, and maintain customer access to the new
store. Staff is also working with Dahl’s
to obtain the necessary construction and permanent easements for the storm
sewer construction and existing sanitary sewer in accordance with the
revised PUD Conceptual Plan approved by the Council on February 11, 2008.
FISCAL IMPACT:
Amount: $748,641 City
Engineer's Estimate
Funding Source: 2007-2008 CIP,
Page Sanitary-5, City-wide Sanitary Sewers, SAE054, Various Funding,
Being: 50% in Sanitary Sewer Funds from
SAE054, and 50% in Storm Water Utility Funds from STE057, Page Storm Water-5,
City-Wide Storm Water Utility Projects
ADDITIONAL INFORMATION:
The Ingersoll
Avenue corridor and the surrounding neighborhood
are within the portion of the City of Des
Moines that is served by the combined sewer
system. It is important to construct the necessary improvements to the
storm and sanitary sewer systems in order to comply with the commitments made
in the Long Term Control Plan (LTCP) submitted to the Iowa Department of
Natural Resources (IDNR). The completed
Ingersoll Run Storm Sewer will provide an outlet for future projects that will
separate combined sewers as required in the Des Moines LTCP. The ultimate proposed Ingersoll Run Basin
Master Plan will include projects to separate the whole system from M.L. King Jr. Parkway
to 42nd Street
between Ingersoll Avenue
and I-235 in the future. This project
will get the backbone of the storm sewer system to the low point of 35th Street,
which will take a significant storm load off the combined sewer.
Dahl’s Foods Store property at 35th Street
and Ingersoll Avenue
is along the alignment of the proposed Ingersoll Run Storm Sewer, which is a
part of the LTCP for the separation of the combined sewer system. Currently,
there is an existing combined sewer crossing the Dahl’s site. The LTCP calls for
the storm sewer to be constructed to the intersection of 32nd Street and Woodland Avenue by
the end of 2009 and to 35th
Street north of Ingersoll Avenue by the end of 2013. City
of Des Moines staff has been in discussion with Dahl’s representatives regarding
the window of opportunity for construction and coordination of schedules for
the City’s proposed storm sewer and the proposed Dahl’s new Ingersoll Avenue
store, for which, on February 11, 2008, the City Council approved the PUD
Conceptual Plan proposed by Foods Inc. (Dahl’s) for property at 3425 Ingersoll Avenue.
The alignment for the new storm sewer will essentially
parallel the existing combined sewer. Construction
of the storm sewer at this alignment needs to be completed during the Dahl’s
construction in order to prevent major disruptions to Dahl’s and extensive
additional storm sewer construction costs. Staff is also working with Dahl’s to
obtain the necessary construction and permanent easements for the proposed storm
sewer construction and existing sanitary sewer in accordance with the revised
PUD Conceptual Plan approved by the Council on February 11, 2008. The new storm sewer will be constructed in
phases and coordinated with the Dahl’s store construction to minimize the disruption, coordinate with their parking
lot construction, and maintain customer access to the new store.
The first phase of storm project from 34th Street and Woodland Avenue to just
east of the existing retaining wall east of the current store must be
constructed before Dahl’s starts construction of their new store loading dock
facility and truck parking. After Dahl’s
demolishes their existing store anticipated being between January and April
2009, the second phase of the storm sewer project will begin with the construction
of the storm sewer from the end of the first phase to approximately half way
across the Dahl’s parking lot. At that
time, Dahl’s contractor will construct the new parking lot over the new storm
sewer. During this phase 2 construction, customers will have access to the west
door of the new store across the west half of the existing parking lot. When Dahl’s completes access to the east door
of the new store, the storm sewer contractor will commence the third phase to
complete construction of the storm sewer to 35th Street. At that time, Dahl’s customers will have
access to the east door of the new store.
This proposed storm sewer project does not include street improvements
on 34th Street
from Ingersoll Avenue
to the proposed Dahl’s truck entrance. Staff
has not had adequate time to coordinate the necessary detailed design work with
Dahl’s for these street improvements to the final location of their truck entrance. In order to meet Dahl’s tight time schedule,
the project needs to be bid very quickly.
Staff will continue to work with Dahl’s to comply with the terms of the
PUD Conceptual Plan approved by the City Council on February 11, 2008. Staff is negotiating with Dahl’s to approve
the permanent storm sewer and sanitary sewer easements for mutual benefit given
the City’s commitment to design, construct, and fund the improvements to 34th
Street from Ingersoll Avenue north to the new Dahl’s truck entrance. When the design is completed, staff would
recommend that these street improvements be included into this storm sewer
project by addendum or change order.
The Engineering Department has
prepared plans, specifications, form of contract documents, and City Engineer’s
estimate for the construction of the Ingersoll Run Storm Sewer - 34th Street to 35th Street,
08-2007-006. The improvement includes
construction of 6' x 6' reinforced concrete box culvert, 12" and 15"
storm sewer, storm manholes, storm intakes, special structure, 8" PCC
pavement, 7" and 8" PCC driveways, 4" and 6" PCC sidewalk,
6" water main relocation, and miscellaneous associated work including
cleanup; in accordance with the contract documents, including Plan File Nos.
479-139/149, and located from 34th Street to 35th Street, between Ingersoll
Avenue and Woodland Avenue.
The estimated construction cost
is $748,641. The proposed plans,
specifications, and form of contract documents are available for public
inspection in the City Engineer's Office.
PREVIOUS COUNCIL ACTION(S):
Date: February 11, 2008
Roll Call Number: 08-247
Action: On
the PUD Conceptual Plan proposed by Foods Inc. (Dahl’s) for property at 3425 Ingersoll Avenue,
(continued from 1-28-08). (Council
Communication No. 08-073) Moved by Hensley to adopt, including a change
to item 9 – the City may consider…will be changed to the City shall
consider… Also, the City will monitor
the traffic on 34th
Street for possible cul-de-sac or barrier. Motion Carried 6-1. Nays: Cownie.
Date: February 11, 2008
Roll Call Number: 08-248
Action: (A) Second
consideration of rezoning ordinance. Moved by Hensley that this ordinance be
considered and given second vote for passage. Motion Carried 6-1. Nays: Cownie.
Date: February 11, 2008
Roll Call Number: 08-249
Action: (B) Final consideration of rezoning ordinance. Moved
by Hensley that the rule requiring that an ordinance must be considered and
voted on for passage at two Council meetings prior to the meeting at which it
is to be finally passed be suspended, that the ordinance be placed upon its
final passage and that the ordinance do now pass, #14,744. Motion Carried 6-1. Nays: Cownie.
Date: March
20, 2006
Roll Call Number: 06-498
Action: Approving
professional services agreement with Veenstra & Kimm, Inc. in conjunction
with The Ingersoll Run Basin Master Plan Study, not to exceed $199,600. (Council
Communication No. 06-144) Moved by Brooks to adopt. Motion Carried 7-0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED ACTIONS AND
FUTURE COMMITMENTS:
Anticipated actions include
public hearing, receive and file bids, designate lowest bidder, and approve
contract and bond; also partial payments to the contractor and final acceptance
of work.