Date
|
March 10, 2008
|
||
|
Agenda Item No. 8B Roll Call No. 08- Communication No. 08-119 Submitted by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Ordering construction of the
following: Southeast Connector - Des
Moines River Bridge with Levee, Sanitary Sewer, and Water Main Relocation -
Receiving bids, (3-18-08), and Setting date of hearing, (4-7-08). (Construction Estimate - $9,975,000).
SYNOPSIS:
Recommend the City Council proceed
with construction of the improvement and set dates to receive bids and hold a
public hearing, as required by Iowa Code, utilizing the method of financing
referenced below. On January 23, 2006, City Council approved the design concept
of a basic bridge with enhancements for the new
FISCAL IMPACT:
Amount: $9,975,000 City
Engineer's Estimate
Funding Source: 2007-2008 CIP,
Page Street-41, Southeast Connector - SW Second to SE Sixth Street, STR214, $10,638,451 in available funding being:
$1,533,690 in TIF, $971,200 in Federal Transportation earmark funds under
NHSX-U-1945(402)--8S-77, $2,970,000 in Federal Transportation earmark funds and
$2,292,000 in Federal Surface Transportation Program funds under
NHSX-U-1945(403)--8S-77, and $2,871,561 in Federal Transportation earmark funds
under NHSX-U-1945(405)--8S-77
ADDITIONAL INFORMATION:
The
IDOT and the City of
The Engineering Department has prepared plans,
specifications, form of contract documents, and City Engineer’s estimate for
the construction of the Southeast Connector -
1. Southeast
Connector:
2. Southeast
Connector: Levee, Sanitary Sewer, and
Water Main Relocation, IDOT Project No. NHSX-U-1945(402)--8S-77, Activity ID
04-2007-010, being construction of approximately 292 LF of 12-inch ductile iron
water main and 542 LF of 48-inch concrete sanitary sewer pipe, along with all
the necessary excavation, selected backfill, compaction, removals, slotted
drains, subdrain, intakes, storm sewer, sanitary sewer, utility access structures,
Hot Mix Asphalt recreation trail, PCC driveway, PCC pavement patches,
contaminated soil handling and disposal, slope protection, traffic control,
safety closures, fence work, silt fence, topsoil, and restoration; all in
accordance with the contract documents including Plan File Nos. 481-276/318.
The
improvement is generally located from the west side of the Des Moines River
near the intersection of
The
estimated construction cost is $9,975,000.
The proposed plans, specifications, and form of contract documents are
available for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date: September 11, 2006
Roll Call Number: 06-1829
Action: Programmatic Agreement with Federal Highway
Administration, Iowa Department of Transportation, and Iowa State Historic
Preservation Office in conjunction with the Southeast Connector Urban Arterial
Projects and Associated Features to define the process for identifying,
evaluating and treating historical properties and archeological resources. (Council Communication No. 06-570) Moved
by Vlassis to adopt. Motion Carried 6-0.
Date: January 23, 2006
Roll Call Number: 06-124
Action: Approving Bridge
Design Concept for Southeast Connector over the
Date: March 7, 2005
Roll Call Number: 05-530
Action: Execution of Iowa Department of Transportation
Agreement. (Council
Communication No. 05-098) Moved
by Hensley to adopt. Motion Carried 7-0.
Date: March 7, 2005
Roll Call Number: 05-531
Action: Execution of Professional Services Agreement
with Kirkham Michael & Associates, (Dale Miller, President,
BOARD/COMMISSION ACTION(S):
Date: July 10, 2007
Roll Call Number: NA
Action: Urban Design Review Board approved the
proposed SE Connector Bridge project. The Board asked that additional information
regarding pedestrian circulation and the planned pathway system be presented
and clarified when the roadway project is submitted in the future.
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Anticipated actions include
public hearing, receive and file bids, designate lowest bidder, and approve
contract and bond; also partial payments to the contractor and final acceptance
of work.
For more information on this and other agenda items, please call the City
Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the second floor
of City Hall,