Council
Communication
Office of the
City Manager
|
|
|
Date
|
April 24, 2008
|
|
Agenda Item No. 62
Roll Call No. 08-
Communication
No. 08-170
Submitted
by: Jeb E. Brewer, P.E.
City Engineer
|
AGENDA HEADING:
Hearing on Ingersoll Run Storm
Sewer – 34th Street to 35th Street: Resolution approving
plans, specifications, form of contract documents, engineer’s estimate, receive
and file bids, and designating lowest responsible bidder as Van Hauen &
Associates, Inc., Mark Van Hauen, CEO/Vice President, 13185 Pineview
Drive, Clive, IA, 50325, $588,000.
SYNOPSIS:
This is a public hearing to
allow for public input on the Ingersoll Run Storm Sewer – 34th Street to 35th Street
and to take the necessary actions as required by Iowa Code to authorize a
contract for construction of the proposed project. This project provides for the construction of
a 6’ X 6’ reinforced concrete box storm sewer across the Dahl’s Foods Store
property at 35th Street
and Ingersoll Avenue. This store site is along the alignment of the
proposed Ingersoll Run Storm Sewer that is a part of the Long Term Control Plan
(LTCP) for the separation of the combined sewer system. The LTCP calls for the storm sewer to be
constructed to the intersection of 32nd
Street and Woodland Avenue by the end of 2009 and to
35th Street north
of Ingersoll Avenue
by the end of 2013. Staff has worked
with Dahl’s to coordinate construction of the sewer in three phases to minimize
the disruption, coordinate with their parking lot construction, and maintain
customer access to the new store.
At its February 25, 2008 meeting, the City Council asked
several questions regarding the easements with Foods Inc. (Dahl’s) and the
costs associated with improvements to 34th
Street north of Ingersoll to the Dahl’s truck
entrance which were required at the PUD hearing. Council requested that information regarding
these questions be provided before the public hearing on the plans and
specifications, presentation of bids, and award of contract on the Ingersoll
Run Storm Sewer from 34th to 35th. Staff has provided additional information in
this Council Communication. The City can
save between $377,000 and $988,000 by accepting the low bid from Van Hauen
& Associates, Inc. for the Alignment 1 work as discussed below and
approving the mutual benefit temporary and permanent easements with Food Inc.,
whereby the City will design and construct the proposed 34th Street
improvements north of Ingersoll Avenue at City cost as part of the Ingersoll
Run Storm Sewer – 34th Street to 35th Street project.
FISCAL IMPACT:
Amount: $588,000
Construction Contract ($748,641 City Engineer's Estimate)
Funding Source: 2007-2008 CIP,
Page Sanitary-5, City-wide Sanitary Sewers, SAE054, various Funding, being: 50% in Sanitary Sewer Funds from SAE054, and
50% in Storm Water Utility Funds from STE057, Page Storm Water-5, City-Wide
Storm Water Utility Projects
ADDITIONAL INFORMATION:
Background
The Ingersoll Avenue
corridor and the surrounding neighborhood are within the portion of the City of
Des Moines that
is served by the combined sewer system. It is important to construct the necessary
improvements to the storm and sanitary sewer systems in order to comply with
the commitments made in the Long Term Control Plan (LTCP) submitted to the Iowa
Department of Natural Resources (IDNR).
The completed Ingersoll Run Storm Sewer will provide an outlet for
future projects that will separate combined sewers as required in the Des
Moines LTCP. The ultimate proposed
Ingersoll Run Basin Master Plan will include projects to separate the whole
system from M.L. King Jr. Parkway
to 42nd Street
between Ingersoll Avenue
and I-235 in the future. This project
will get the backbone of the storm sewer system to the low point of 35th Street,
which will take a significant storm load off the combined sewer.
The Dahl’s Foods Store property at 35th Street and Ingersoll Avenue is
along the alignment of the proposed Ingersoll Run Storm Sewer, which is a part
of the LTCP for the separation of the combined sewer system. There is an
existing combined sewer crossing the Dahl’s site. The LTCP calls for
the storm sewer to be constructed to the intersection of 32nd Street and Woodland Avenue by
the end of 2009 and to 35th
Street north of Ingersoll Avenue by the end of 2013. City
of Des Moines staff has been in discussion with Dahl’s representatives
regarding the window of opportunity for construction and coordination of
schedules for the City’s proposed storm sewer and the proposed Dahl’s new
Ingersoll Avenue store, for which, on February 11, 2008, the City Council
approved the PUD Conceptual Plan proposed by Foods Inc. (Dahl’s) for property
at 3425 Ingersoll Avenue.
The alignment for the new storm sewer will essentially
parallel the existing combined sewer.
Construction of the storm sewer at this alignment needs to be completed
during the Dahl’s construction in order to prevent major disruptions to Dahl’s
and extensive additional storm sewer construction costs. Staff is also working
with Dahl’s to obtain the necessary construction and permanent easements for
the proposed storm sewer construction and existing sanitary sewer in accordance
with the revised PUD Conceptual Plan approved by the Council on February 11,
2008. The new storm sewer will be
constructed in phases and coordinated with the Dahl’s store construction to minimize the disruption, coordinate with their parking
lot construction, and maintain customer access to the new store.
The
first phase of storm project from 34th
Street and Woodland Avenue to just east of the
existing retaining wall east of the current store must be constructed before
Dahl’s starts construction of their new store loading dock facility and truck
parking. After Dahl’s demolishes their
existing store, anticipated being between January and April 2009, the second
phase of the storm sewer project will begin with the construction of the storm
sewer from the end of the first phase to approximately half way across the
Dahl’s parking lot. At that time, Dahl’s
contractor will construct the new parking lot over the new storm sewer. During
this phase 2 construction, customers will have access to the west door of the
new store across the west half of the existing parking lot. When Dahl’s completes access to the east door
of the new store, the storm sewer contractor will commence the third phase to
complete construction of the storm sewer to 35th Street. At that time, Dahl’s customers will have
access to the east door of the new store.
Additional
Information requested by the City Council on February 25, 2008.
At its February 25, 2008 meeting, the City Council asked
several questions that they wanted answered before the public hearing on the
plans and specifications, presentation of bids, and award of contract on the
Ingersoll Run Storm Sewer from 34th to 35th being:
1. How
will the cost for construction of 34th Street
from Ingersoll to Dahl's truck entrance be shared?
2. Provide
a complete description of the proposed easement and what is the cost to the City?
3. At
the PUD hearing, there was an indication that there would be savings to the
City by going across Dahl's parking lot. Numbers like $500,000 were given. What is the estimate for that savings?
The answers to these questions are provided below.
Engineer’s Estimate
for improvements to 34th Street north of Ingersoll Avenue
Estimates have been prepared by the consultant for the Ingersoll
Run Storm Sewer – 34th Street to 35th Street project to
remove the exiting 34th Street pavement and construct a 31-foot wide
street with 8-inch thick Portland Cement Concrete from Ingersoll Avenue north
through the intersection with Cresent Drive, and also construct new curbs and
an asphalt overlay from Cresent Drive north to the pavement replaced for the
proposed storm sewer construction.. The
total estimated cost for this work is $124,500 plus approximately $12,000 for
the consultants design and construction phase
services for a total of $136,500. This
estimate includes $10,600 to construct the new curbs and asphalt overlay on the
section of 34th Street from Cresent Drive north to the proposed
storm sewer construction, which is not required as part of the Dahl’s driveway
construction.; however, it will complete the street reconstruction from
Ingersoll Avenue north to Woodland Avenue..
The City Engineer issued an addendum to the Ingersoll Run Storm Sewer – 34th Street
to 35th Street
project to include these proposed 34th
Street improvements into the storm sewer
project. Therefore, the storm sewer
project must be increased by the 34th
Street cost.
The cost of this improvement is proposed to be offset by the savings in
easement costs donated by Dahl’s as discussed below.
Estimated Fair Market
Value of the Proposed Easements
The Engineering Department has estimated the area needed for
the proposed temporary and permanent easements across the Dahl’s property and
the fair market value as follows:
- Permanent
Easement for proposed Storm Sewer:
This proposed easement is 30-feet wide and centered over the
proposed storm sewer resulting in an area of 15,940 square feet valued at
$55,790.
- Permanent
Easement for existing Combined Sewer: This proposed easement is 30-feet
wide and centered over the existing combined sewer resulting in an area of
14,150 square feet valued at $49,525.
- Temporary
Easement for proposed construction: This proposed easement is
approximately 25-feet wide on each side of the proposed storm sewer
resulting in an area of 24,250 square feet valued at $26,219.
The easement estimates were based on a land value estimate
of $7.00 per square foot from property sales in the area. The Polk County Assessor’s land value for the
Foods, Inc. (Dahl’s) property is $6.56 per square foot. The total estimated easement cost for access
across the Dahl’s property at 3425
Ingersoll Avenue for the existing combined sewer
and the proposed storm sewer construction is $131,534. Even if the proposed storm sewer is not
constructed across the Dahl’s property, the City will still need to negotiate a
permanent easement for the existing sanitary sewer.
Since the estimated value of the needed temporary and permanent
easements ($131,534) is approximately equal to the estimated cost for the
proposed 34th Street improvements north of Ingersoll Avenue
($136,500), staff began negotiations with Foods, Inc. to acquire the necessary
temporary and permanent easements based on mutual benefit with the City to
design and construct the proposed 34th Street improvements north of
Ingersoll Avenue at City cost as part of the Ingersoll Run Storm Sewer – 34th
Street to 35th Street project.
Bid prices for 34th Street
improvements north of Ingersoll
Avenue
The original estimate presented to the City Council on
February 25, 2008 for the Ingersoll Run Storm Sewer – 34th Street to 35th Street
project was $748,641. However, as stated
above, the City Engineer issued an addendum to include the 34th Street improvements north
of Ingersoll estimated at $124,566 into the contract, which makes the revised
Engineer’s estimate $873,207.
On March 11, 2008, the City received bids on the Ingersoll
Run Storm Sewer – 34th
Street to 35th Street project. The low bid was received from Van Hauen &
Associates in the amount of $588,000, which was almost 33% below the Engineer’s
estimate of $873,207. Engineering
Department Staff have calculated the cost for the 34th Street improvements north
of Ingersoll based on the actual bid prices to be $118,815, plus approximately
$12,000 for the consultants design and
construction phase services for a total of $130,815. This $130,815 is approximately equal to the
estimated value of the needed temporary and permanent easements ($131,534) as
shown above. Therefore, staff is
continuing to negotiate with Foods, Inc. to acquire the necessary temporary and
permanent easements based on mutual benefit with the City to design and
construct the proposed 34th Street improvements north of Ingersoll
Avenue at City cost as part of the Ingersoll Run Storm Sewer – 34th
Street to 35th Street project.
After the permanent and temporary easements have been executed by Foods,
Inc, they will be presented to the Mayor for acceptance and signature on behalf
of the City of Des Moines
in accordance with the roll call.
Alternate
Construction Alignments
Staff evaluated three alternate alignments for the proposed
storm sewer to be constructed generally from the intersection of 34th Street
and Woodland Avenue
to the low-point on 35th
Street north of Ingersoll Avenue being:
- Alignment
1 being south on 34th
Street and diagonally west across Dahl’s
property to 35th
Street. This is the project for which bids
were received on March 11, 2008; however, for consistency, the estimated
cost of $748,641 will be used to calculate the estimated savings when
compared to the estimates for the other alignments. This option would require construction
diagonally across the Dahl’s parking area south of the new store and would
generally follow the natural low drainage way from 35th to 34th. Staff has worked with Dahl’s to
coordinate construction of the sewer in three phases to minimize the
disruption, coordinate with their parking lot construction, and maintain customer
access to the new store. This
option is recommended.
- Alternate
2 being west on Woodland
Avenue to 35th Street and then
south to the low point. This
alignment is approximately 115 feet longer than Alternate 1 and would
require construction through the relatively narrow corridor along Woodland Avenue. The storm sewer construction would be
very deep, require complete full width removal and replacement of Woodland Avenue,
and would be greatly effected by construction of the Dahl’s store;
therefore two estimates have been prepared being:
- Construction
before Dahl’s new store is constructed.
If the storm sewer is built before the new Dahl’s store, the City
could construct the sewer with normal open-cut construction; however,
because of the width of the trench, an easement would be required from
Dahl’s and part of the parking lot along Woodland would need to be removed and
replaced. The estimate for
Alternate 2 with open-cut is $916,044, which is $167,403 more than the
$748,641 estimate for Alternate 1.
- Construction
after Dahl’s new store is constructed.
If the storm sewer is built after the new Dahl’s store, there are
significant technical concerns relative to the ability to construct the
storm sewer adjacent to the building in close proximity to the south
right-of-way line of Woodland
Avenue.
If these concerns can be addressed, the construction would require
an estimated $200,000 in steel sheeting to be driven and left in place to
protect the store footings. In
addition, because of the very small construction zone, dirt excavated to
construct the storm sewer would need to be trucked out, stockpiled, and
then trucked back in after the sewer is built, with this additional
handling estimated at $150,000.
The estimate for Alternate 2 with steel sheeting is $1,266,000,
which is $517,359 more than the $748,641 estimate for Alternate 1.
- Alternate
3 being south on 34th
Street to Ingersoll Avenue, west to 35th Street,
and then north to the low-point. This alignment is approximately 580 feet
longer than Alternate 1 and would require removal and replacement of 34th Street
from Woodland
to Ingersoll, removal and replacement of at least the two westbound lanes
of Ingersoll, and removal and replacement on 35th Street
(approximately 3,000 square yards of pavement removal and replacement
total). This sewer construction
would also be deep on 34th Street and Ingersoll Avenue, and
would be disruptive to traffic and utilities. In addition, if this route is
constructed after completion of the new Dahl’s Store, it would require
removal of 34th
Street, which is the truck access to the
store, and also removal of the drive entrance to Ingersoll, which is one
of the two entrances to the store and the closest access to the gas
station. This option would be very disruptive to Dahl’s. The estimate for Alternate 3 is
$1,527,000, which is $778,143 more than the $748,641 estimate for
Alternate 1.
Summary
The estimated costs of the various alignments are tabulated
below for various options being:
- Estimated
construction cost only.
- Estimated
construction costs plus easement costs.
For Alignment 1 the estimated cost for the 34th Street Improvements
($136,500) was used instead of the estimated easement cost of $131,534. Alignments 2 and 3 do not require
acquisition for the storm sewer easements: however, the $49,525 permanent
easement for the existing sanitary sewer is still required.
- Actual
bid prices.
Based on these estimated costs, the lowest cost alternate is
Alignment 1, which is the recommended project to acquire easements from Dahl’s
and construct the proposed storm sewer across the Dahl’s property in three
phases to minimize the disruption, coordinate with their parking lot
construction, and maintain customer access to the new Dahl’s store.
|
Description
|
Estimated Construction Cost
|
Additional Cost over Alignment 1
|
Estimated Easement Cost
|
Easement plus Construction cost
estimate
|
Additional Cost over Alignment 1
$885,141 estimate
|
Additional Cost based on low bid of
$588,000
|
|
Alignment
1 (Project bid)
|
748,641
|
0
|
136,500
|
885,141
|
0
|
0
|
|
Alignment
2 (Before store)
|
916,044
|
167,397
|
49,525
|
965,569
|
80,428
|
377,569
|
|
Alignment
2 (After store)
|
1,266,000
|
517,359
|
49,525
|
1,315,525
|
430,384
|
727,525
|
|
Alignment
3
|
1,527,000
|
778,359
|
49,525
|
1,576,525
|
691,384
|
988,525
|
The City can save between $377,000 and $988,000 by accepting
the low bid from Van Hauen & Associates, Inc. for the Alignment 1 work and approving the
mutual benefit temporary and permanent easements with Food Inc. whereby the
City will design and construct the proposed 34th Street improvements
north of Ingersoll Avenue at City cost as part of the Ingersoll Run Storm Sewer
– 34th Street to 35th Street project.
Recommended Action
on bids received March 11, 2008
On February 25, 2008, under Roll Call No. 08-284, the City
Council received and filed plans, specifications, form of contract documents,
and City Engineer's estimate for the construction of the Ingersoll Run Storm
Sewer – 34th Street to 35th Street. Before the City Council can enter into a
contract, a public hearing must be held to approve the proposed plans,
specifications, and form of contract documents and engineer's estimate for the
construction of the Ingersoll Run Storm Sewer – 34th Street to 35th
Street, 08-2007-006. The improvement
includes construction of 6' x 6' reinforced concrete box culvert, 12" and
15" storm sewer, storm manholes, storm intakes, special structure, 8"
PCC pavement, 7" and 8" PCC driveways, 4" and 6" PCC
sidewalk, 6" water main relocation, and miscellaneous associated work
including cleanup; in accordance with the contract documents, including Plan
File Nos. 479-139/149, and located from 34th Street to 35th
Street, between Ingersoll Avenue and Woodland Avenue, Des Moines, Iowa.
Sealed bids for said improvement
were submitted by the following bidders:
Van Hauen & Associates,
Inc., Clive, IA
The Underground Company, Ltd., Carlisle, IA
Priority Excavating LLC, Waukee, IA
Corell Contractor, Inc., West Des Moines, IA
Reilly Construction Co., Inc.,
Ossian, IA
H & W Contracting LLC, Sioux Falls, SD
Eco-Tech Construction, LLC,
Grimes, IA, Bid read under advisement
The bids were received and
opened at a public meeting presided over by the City Engineer in the City
Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray Drive, Des
Moines, Iowa at 11:00 a.m. on March 11, 2008.
The City Engineer has determined
that the lowest responsive, responsible bid for the construction of said
improvement was submitted by Van Hauen & Associates, Inc. in the amount of
$588,000, and said bid should be accepted. The Finance Director has determined that funds
are available for said improvement as stated above.
PREVIOUS COUNCIL ACTION(S):
Date: February 25, 2008
Roll Call Number: 08-284
Action: Ordering
construction of the following: Ingersoll
Run Storm Sewer – 34th
Street to 35th Street - Receiving of
bids, (3-11-08), and Setting date of hearing, (3-24-08). (Construction Estimate $748,641) (Council
Communication No. 08-086) Moved by Hensley to adopt. Motion Carried 7-0.
Date: February 11, 2008
Roll Call Number: 08-247
Action: On
the PUD Conceptual Plan proposed by Foods Inc. (Dahl’s) for property at 3425 Ingersoll Avenue,
(continued from 1-28-08). (Council
Communication No. 08-073) Moved by Hensley to adopt, including a change
to item 9 – the City may consider…will be changed to the City shall
consider… Also, the City will monitor
the traffic on 34th
Street for possible cul-de-sac or barrier. Motion Carried 6-1. Nays:
Cownie.
Date: February 11, 2008
Roll Call Number: 08-248
Action: (A) Second
consideration of rezoning ordinance. Moved by Hensley that this ordinance be
considered and given second vote for passage.
Motion Carried 6-1. Nays: Cownie.
Date: February 11, 2008
Roll Call Number: 08-249
Action: (B) Final consideration of rezoning
ordinance. Moved by Hensley that the rule requiring that an ordinance must be
considered and voted on for passage at two Council meetings prior to the
meeting at which it is to be finally passed be suspended, that the ordinance be
placed upon its final passage and that the ordinance do now pass, #14,744. Motion Carried 6-1. Nays:
Cownie.
Date: March 20, 2006
Roll Call Number: 06-498
Action: Approving
professional services agreement with Veenstra & Kimm, Inc. in conjunction
with The Ingersoll Run Basin Master Plan Study, not to exceed $199,600. (Council
Communication No. 06-144) Moved by Brooks to adopt. Motion Carried 7-0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED ACTIONS AND
FUTURE COMMITMENTS:
Partial payments to the
contractor and final acceptance of work.
For more information on this and other agenda items,
please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office
on the second floor of City Hall, 400
Robert D. Ray Drive. Council agendas are available to the public
at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council
meeting. Citizens can also request to receive meeting notices and agendas by
email by calling the Clerk’s Office or sending their request via email to
cityclerk@dmgov.org.