Council
Communication
Office of the
City Manager
|
|
|
Date
|
April 7, 2008
|
|
Agenda Item No. 55
Roll Call No. 08-
Communication
No. 08-198
Submitted
by: Jeb E. Brewer, P.E.
City Engineer
|
AGENDA HEADING:
Hearing on Fleur
Drive Bridge
over the Raccoon River rehabilitation: Resolution approving plans, specifications,
form of contract documents, engineer’s estimate, receive and file bids, and
designating lowest responsible bidder as The Truesdell Corporation of
Wisconsin, Inc., Kurt L. Clink, President, $1,424,424.
SYNOPSIS:
This is a public hearing to
allow for public input on the Fleur Drive Bridge
over the Raccoon River rehabilitation and to take
the necessary actions as required by Iowa Code to authorize a contract for
construction of the proposed project. Recent
bridge inspections have found that this bridge, which was originally built in
1936 and rehabilitated in 1970, is showing signs of deterioration. This project will rehabilitate the
superstructure and substructure, including cleaning and painting of the
structural steel girders, thereby extending the service life of the bridge by
20 to 30 years.
FISCAL IMPACT:
Amount: $1,424,424
Construction Contract ($1,577,664 City Engineer's Estimate)
Funding Source: 2007-2008 CIP,
Page Bridge-17, Structural Repair - Corrosion Protection, BRV039, Being: $800,000 in Tax Increment Funds and $624,424
in G. O. Bonds
ADDITIONAL INFORMATION:
On February 25, 2008, under Roll
Call No. 08-283, the City Council received and filed plans, specifications,
form of contract documents, and City Engineer's estimate for the construction
of the Fleur Drive Bridge
over the Raccoon River Rehabilitation.
Before the City Council can enter into a contract, it must hold a public
hearing and approve the proposed plans, specifications, and form of contract
documents and engineer's estimate for the construction of the Fleur Drive
Bridge over the Raccoon
River Rehabilitation, 12-2007-005. The
improvement includes rehabilitation of the existing bridge superstructure and
substructure including concrete removal, structural concrete (bridge),
structural steel, reinforced neoprene, steel extrusion joint with neoprene,
concrete repair (median and sidewalk), concrete repair (barrier rail), concrete
repair (substructure), bridge floor overlay repairs, bridge floor overlay (full
depth), sidewalk removal and replacement, jack girders and reset bearings, trim
girder ends, drain pipe, epoxy injection, pavement joint repairs, reinforced
neoprene trough installation, carbon fiber reinforcing polymer furnish and
install, approach repairs, curb repairs, concrete waterproofing, containment,
blast cleaning structural steel, paint waste transport/disposal, painting of
structural steel, pavement markings/symbols and message boards, construction
survey, project sign, traffic control and mobilization; all work in accordance
with the contract documents including Plan File Nos. 486-082/134, on the Fleur
Drive Bridge over the Raccoon River in Des Moines, Iowa.
Sealed bids for said improvement
were submitted by the following bidders:
The Truesdell Corporation of
Wisconsin, Inc., Phoenix, AZ
Cramer and Associates, Inc.,
Grimes, IA
Herberger Construction Co.,
Inc., Indianola, IA
United Contractors, Inc., Johnston, IA
The bids were received and
opened at a public meeting presided over by the City Engineer in the City
Council Chambers, 2nd Floor, City Hall, 400 Robert D Ray Drive, Des Moines,
Iowa at 11:00 a.m. on March 25, 2008.
The Truesdell Corporation of
Wisconsin, Inc., Kurt L. Clink, President, 1310 W 23rd Street, Phoenix,
AZ, 85282,
submitted the lowest bid; however, has not previously been awarded any
contracts by the City of Des Moines. Engineering Staff has investigated The
Truesdell Corporation of Wisconsin, Inc., which has corporate offices in Phoenix, AZ,
and has a branch office at N115W18835
Edison Drive, Germantown, WI, 53022. The Truesdell Corporation of Wisconsin, Inc.
is not prequalified by the Iowa Department of Transportation, but is
prequalified by the following Departments of Transportation (DOT):
·
Illinois DOT for Structural Repair, Grouting and Demolition;
·
Indiana
DOT for General Construction - Bridges, Viaducts, Elevated Highways, Dams and
Dikes;
·
Wisconsin DOT
for General Construction, Bridge Painting, Structures and Incidental;
·
Missouri
Highway as a Prime Contractor.
The Fleur Drive
Bridge over the Raccoon
River Rehabilitation project includes rehabilitation of the existing bridge
superstructure and substructure, which would generally be included in the DOT prequalification
categories of those listed above. The
Truesdell Corporation of Wisconsin, Inc. is licensed to do business in Iowa by the Iowa
Secretary of State and has applied with Iowa Work Force Development.
The City Engineer has determined
that the lowest responsive, responsible bid for the construction of said
improvement was submitted by The Truesdell Corporation of Wisconsin, Inc., Kurt
L. Clink, President, 1310 W 23rd
Street, Phoenix, AZ, 85282
in the amount of $1,424,424, and said bid should be accepted. The
Finance Director has determined that funds are available for said improvement
as stated above.
PREVIOUS COUNCIL ACTION(S):
Date: February 25, 2008
Roll Call Number: 08-283
Action: Ordering
construction of the following: Fleur
Drive Bridge
over the Raccoon River Rehabilitation – Receiving of bids, (3-25-08), and
Setting date of hearing, (4-7-08). (Construction
Estimate - $1,577,664). Council Communication No. 08-087) Moved by Hensley to adopt. Motion Carried 7-0.
Date: May 7, 2007
Roll
Call Number: 07-841
Action: Approving Professional Services
Agreement for the following:
(B) Evaluation,
design, and construction phase services for the Fleur Drive
Bridge over the Raccoon
River Rehabilitation, Shuck-Britson, Inc., not to exceed $188,260. (Council
Communication No. 07-265) Moved by Vlassis to adopt. Motion Carried 7-0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED ACTIONS AND
FUTURE COMMITMENTS:
Partial payments to the
contractor and final acceptance of work.
For more
information on this and other agenda items, please call the City Clerk’s Office
at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall, 400 Robert D Ray Drive. Council agendas are available to the public
at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council
meeting. Citizens can also request to
receive meeting notices and agendas by email by calling the Clerk’s Office or
sending their request via email to cityclerk@dmgov.org.