Agenda Item No. 6C Roll Call No. 08- Communication
No. 08-334 Submitted
by: Jeb E. Brewer, P.E. City Engineer
|
||||
AGENDA HEADING:
Ordering construction of the following: 2008 HMA Pavement Scarification & Resurfacing - receiving bids, (7-1-08), and setting date of hearing, (7-14-08). (Construction Estimate - $798,715).
SYNOPSIS:
Recommend the City Council proceed with construction of the improvement and set dates to receive bids and hold a public hearing, as required by Iowa Code, utilizing the method of financing referenced below. This project provides for timely maintenance of residential and arterial streets utilizing surface scarification and hot mix asphalt overlay to improve the surface condition and extend the useful service life of the streets.
FISCAL IMPACT:
Amount: $798,715 City Engineer's Estimate
Funding Source: 2008-2009 CIP,
Page Street-6, Asphaltic Paving Restoration Program, STR003, Being: $463,995 in G. O. Bonds from STR003 and
$334,720 in TIF-Backed G. O. Bonds from
ADDITIONAL INFORMATION:
The Engineering Department has prepared plans, specifications, form of contract documents, and City Engineer’s estimate for the construction of the 2008 HMA Pavement Scarification & Resurfacing, 06-2008-015. The improvement includes:
1. Scarification of two (2) inch average depth
of asphalt street surfaces with specified milling machine and equipment in a
cooperative effort with the City of
•
• Crown Lane from
•
• College Avenue from
•
•
•
•
• Hunter Avenue from
• Stephenson Way from
•
•
2. Furnish
all labor, materials and equipment necessary to construct a two (2) inch
average thickness pavement scarification and HMA surfacing on existing
asphaltic street surface; together with other incidental and related work; all
in accordance with the contract documents at the following locations within the
City of
•
• Bowdoin Street from
• Briarcliff Drive from
•
• Grand Avenue from
• Dean Avenue from
• Redhead Road from E Court Avenue to
•
•
The estimated construction cost is $798,715. The proposed plans, specifications, and form of contract documents are available for public inspection in the City Engineer's Office.
PREVIOUS COUNCIL
ACTION(S): NONE
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Anticipated actions include public hearing, receive and file bids, designate lowest bidder, and approve contract and bond; also partial payments to the contractor and final acceptance of work.
For more
information on this and other agenda items, please call the City Clerk’s Office
at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall,