Date
|
July 14, 2008
|
|
|
Agenda
Item No. 7 Roll
Call No. 08- Communication No. 08-399 Submitted by: Jeb E. Brewer,
|
||||
AGENDA
HEADING:
Approving and
authorizing the execution of Iowa Department of Transportation (IDOT) Change
Order No. 1 to Ingersoll Run Phase 2 Storm Sewer Outlet not to exceed City cost
of $64,665.83.
SYNOPSIS:
Approval of
Change Order No. 1 as prepared by IDOT in the amount not to exceed $71,338.88,
for the cost to add 30-inch storm sewer on 29th Street and 31st
Street, to remove the Ingersoll Avenue Streetscape project storm sewers from
the combined sewer, and connect those sewers to the storm sewer system
constructed as part of the Ingersoll Run Phase 2 Storm Sewer Outlet.
FISCAL
IMPACT:
Amount: $64,665.83
Funding Source: 2008-2009 CIP, Page Street-21, I-235 Storm
and Sanitary Sewer Improvements, STR197, TIF Bonds and Storm
and Sanitary Sewer
ADDITIONAL
INFORMATION:
On December 17,
2007, under Roll Call No. 07-2358, the City Council approved a preconstruction
agreement with Iowa DOT for Ingersoll Run Phase 2 Storm Sewer related to I-235,
where the City will reimburse Iowa DOT an estimated 55% of the storm sewer
cost, 100% for any enhanced storm capacity, and 100% of sanitary sewer
cost. The repayment to begin in FY
2007-08. As part of this agreement,
change orders exceeding $25,000 in additional City contribution are to be
approved by the Des Moines City Council.
Change
Order No. 1 will construct storm sewers to connect the Ingersoll Avenue
Streetscape project storm sewer outlets to the Ingersoll Run Phase 2 Storm
Sewer project. At the time that the IDOT
designed and bid the Ingersoll Run Phase 2 Storm Sewer project, the City of
Additional
watering for the sod that will be installed on the project is included. This work is necessary for the overall
drainage plan to remove the storm water from the combined sewer within the
Ingersoll basin. The change order
has been reviewed by the City’s representative, Veenstra and Kimm, Inc., and
found to be reasonable. The City’s share
of Change Order No. 1 is $64,665.83, and the IDOT share is $6,673.05. The total change order is for $71,338.88.
PREVIOUS COUNCIL ACTION(S):
Date:
December 17, 2007
Roll Call
Number: 07-2358
Action: Approving
and authorizing execution of Iowa Department of Transportation (IDOT)
Preconstruction Agreement for the Ingersoll Run Phase 2 Storm Sewer
Outlet. (Council
Communication No. 07-741) Moved by Hensley to adopt. Motion Carried 6-1.
Date: August
31, 2000
Roll Call
Number: 00-3634
Action: Approving
Iowa Department of Transportation Predesign Agreement for Interstate 235, from
the west City limits to the north City limits. (Council Communication No. 00-411). Moved by McPherson to
adopt. Motion Carried 4-2-1. Nays: Brooks and Vlassis. Absent: Flagg.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED ACTIONS
AND FUTURE COMMITMENTS: NONE