Date
|
July 14, 2008
|
||
|
Agenda Item No. 70 Roll Call No. 08- Communication
No. 08-402 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Hearing
on
SYNOPSIS:
This
is a public hearing to allow for public input on the
FISCAL IMPACT:
Amount: $345,724.53 Construction Contract ($315,000 City Engineer's Estimate)
Funding
Source:
2008-2009 CIP, Page Traffic-9, Traffic Signal Installation -
· $150,000 Maximum in Iowa DOT Traffic Safety Improvement Funds for eligible construction only;
· $150,000 Maximum in FHWA Surface Transportation Program (STP) funds for eligible construction only;
· $15,000 in Tax Increment Funds from Traffic Signal Installation – Crocker Street at Fifth Avenue, Sixth Avenue, & Seventh Street, Page Traffic Control-9, TFC096 with a transfer of $63,000 in G. O. Bonds from City-wide Signals, Channelization, and School Crossing Protection Program, Page Traffic Control-5, TFC091
ADDITIONAL INFORMATION:
On
June 9, 2008, under Roll Call No. 08-955, the City Council received and filed
plans, specifications, form of contract documents, and City Engineer's estimate
for the construction of the
the existing temporary traffic
signals at the intersections of
Sealed bids for said improvement were submitted by the following bidders:
Baker
Electric, Inc.,
The
bids, in accordance with a previously approved Iowa Department of Transportation
(IDOT) Agreement, were received and opened by IDOT on June 17, 2008. The only bid received by the IDOT was in the
amount of $345,724.53, which is 9.8% over the Engineer’s Estimate of $315,000,
and staff recommends acceptance. The
City Engineer has determined that the lowest responsive, responsible bid for
the construction of said improvement was submitted by Baker Electric, Inc. in
the amount of $345,724.53, and said bid should be accepted. The Finance Director has determined that
funds are available for said improvement as stated above.
PREVIOUS COUNCIL ACTION(S):
Date: June 9, 2008
Roll Call Number: 08-955
Action: Ordering construction of the following: Crocker Street at 5th Avenue, 6th Avenue & 7th Street Traffic Signal Installation – Receiving of bids, (6-17-08), and Setting date of hearing, (7-14-08). (Construction Estimate - $315,000). (Council Communication No. 08-345) Moved by Hensley to adopt. Motion Carried 7-0.
Date: February 12, 2007
Roll Call Number: 07-200
Action: Approving Iowa Department of Transportation
Agreement for
Date: July 24, 2006
Roll Call Number: 06-1427
Action: Approving execution of Iowa Department of
Transportation Agreement for
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Partial payments to the contractor and final acceptance of work.
For more information on this and other agenda items, please call
the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the
second floor of City Hall,