Date
|
July 28, 2008
|
||
|
Agenda Item No. 49 Roll Call No. 08- Communication
No. 08-443 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Hearing on High Street Realignment - 10th Street to 14th Street - Phase 1: Resolution approving plans, specifications, form of contract documents, engineer’s estimate, receive and file bids, and designating lowest responsible bidder as Sternquist Construction Inc., Britt Sternquist, President, $677,698.70.
SYNOPSIS:
This is a public hearing to
allow for public input on the High Street Realignment -
FISCAL IMPACT:
Amount: $677,698.70 Construction Contract ($680,000 City Engineer's Estimate)
Funding Source: 2008-2009 CIP,
Page Street-18, High Street Realignment -
ADDITIONAL INFORMATION:
On June 23, 2008, under Roll Call No. 08-1091, the City Council received and filed plans, specifications, form of contract documents, and City Engineer's estimate for the construction of the High Street Realignment - 10th Street to 14th Street - Phase 1. Before the City Council can enter into a contract, it must hold a public hearing and approve the proposed plans, specifications, and form of contract documents and engineer's estimate for the construction of the High Street Realignment - 10th Street to 14th Street - Phase 1, 06-2008-004. The improvement includes clearing and grubbing, pavement removal and replacement, sidewalk removal and replacement, excavation, storm sewer, hydrant relocation, traffic signals, pavement markings, construction survey, sodding and site restoration; all in accordance with the contract documents including Plan File Nos. 490-10/50 at High Street from 10th Street to 12th Street, Des Moines, Iowa.
Sealed bids for said improvement were submitted by the following bidders:
Sternquist
Construction Inc., Indianola, IA
Elder
Corporation, Des Moines, IA
Corell
Contractor, Inc., West Des Moines, IA
Concrete
Technologies, Inc., Urbandale, IA
Hawkeye Paving Corp.,
The bids were received and opened at a public meeting presided over by the City Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D Ray Drive, Des Moines, Iowa at 11:00 a.m. on July 15, 2008.
The City Engineer has determined
that the lowest responsive, responsible bid for the construction of said
improvement was submitted by Sternquist Construction Inc., Britt Sternquist,
President,
PREVIOUS COUNCIL ACTION(S):
Date: June 23, 2008
Roll Call Number: 08-1091
Action: Ordering construction of the following: High Street Realignment – 10th Street to 14th Street – Phase 1 – Receiving of bids, (7-15-08), and Setting date of hearing, (7-28-08). (Construction Estimate - $680,000). (Council Communication No. 08-374) Moved by Vlassis to adopt. Motion Carried 7-0.
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Partial payments to the contractor and final acceptance of work.