|
Council |
Date |
January
26, 2009 |
||
|
Agenda
Item No. 6 Roll
Call No. 09- Communication
No. 09-039 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA
HEADING:
Ordering
construction of the following: Ashworth
Pool Filter Replacement - receiving bids, (2-24-09), and setting date of
hearing, (3-9-09). (Construction
Estimate - $285,000).
SYNOPSIS:
Recommend
the City Council proceed with construction of the improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below. This
project provides for the replacement of the existing vacuum sand filter system,
which is near the end of its useful life and is not in compliance with current
Iowa Department of Health Standards, with a pressure sand filter system. Replacement of the filter system should
improve water clarity in the pool and should reduce the frequency and staff
time required to backwash the filters.
Construction will occur after the swimming pool
closes for the season next fall.
FISCAL
IMPACT:
Amount: $285,000 City Engineer's Estimate ($240,000
base bid and $45,000 add alternate to replace the pool heater)
Funding
Source: 2008-2009 CIP, Page
Parks-27, Swimming Pools and Aquatic Infrastructure, PKS153, being G. O. Bonds
with a transfer of $285,000 in G. O. Bonds from Park Redevelopment, Page
Parks-19, PKS100.
ADDITIONAL
INFORMATION:
Constructed
in 1983, the Ashworth Pool is similar to many pools constructed during the
time, consisting of an L-shaped structure with diving and an adjacent shallow
wading area. The filter system for
Ashworth Pool is the original vacuum sand filter, located in the adjacent
filter building at an elevation below the pool water level.
Concerns
regarding the Ashworth pool include operational issues and the capacity of the
filter to maintain the pool water quality.
The filter requires frequent backwashing, which is also
ineffective. A key issue with vacuum
sand filters is the potential for “air binding”. When air binding occurs, air bubbles
accumulate within the filter sand bed.
The air bubbles fill the small gaps between sand grains, thus preventing
dirt and debris from having a place to be captured within the filter. The filter bed can become so filled with air
bubbles that the filter cannot function properly. The backwashing process forces the air
bubbles to leave the filter.
The
existing filter system was designed for pool recirculation and water treatment
standards that were appropriate for 1983, which included an eight-hour turnover
period (time that it takes to effectively remove, filter, and chemically treat
the entire volume of water for the pool).
However, the standards have changed since the date of construction,
decreasing the turnover period to six-hours for the lap pool and two-hours for
the shallow wading area. Decreasing the
pool turnover period requires an increase in the rate of recirculation and
filtration. The existing filter system
does not have the capacity to meet the current standards.
A
new filter system would meet the current standards, improve the water clarity,
and reduce the maintenance required. The
proposed system includes above-grade pressure tanks, located to the north of
the filter building. The internal
components of the existing vacuum sand filter would be removed and the vessel
would be utilized as a surge tank.
The
Engineering Department has prepared plans, specifications, form of contract
documents, and City Engineer’s estimate for the construction of the Ashworth
Pool Filter Replacement, 11-2009-008.
The improvement includes replacement of the existing vacuum sand filter
system with a pressure sand filter system, demolition and structural
modifications to the filter building, painting, mechanical, electrical,
concrete work, clean up and debris disposal all in accordance with the contract
documents including Plan File Nos. 495-1/21 at Ashworth Swimming Pool, 102 45th
Street, Des Moines, Iowa.
The
estimated construction cost is $285,000.
The proposed plans, specifications, and form of contract documents are
available for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S): NONE
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Anticipated
actions include public hearing, receive and file bids, designate lowest bidder,
and approve contract and bond; also partial payments to the contractor and
final acceptance of work.
For more information on this
and other agenda items, please call the City Clerk’s Office at 515-283-4209 or
visit the Clerk’s Office on the second floor of City Hall, 400 Robert D Ray
Drive. Council agendas are available to
the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s
Council meeting. Citizens can also
request to receive meeting notices and agendas by email by calling the Clerk’s
Office or sending their request via email to cityclerk@dmgov.org.