Council |
Date |
February
9, 2009 |
||
|
Agenda Item No. 7C Roll Call No. 09- Communication
No. 09-069 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA
HEADING:
Ordering
construction of the following: Southeast
Connector Paving - SE 4th Street to SE 9th Street - Receiving bids, (2-17-09),
and Setting date of hearing, (3-9-09). (Construction Estimate - $3,750,000).
SYNOPSIS:
Recommend
the City Council proceed with construction of this improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below. This project is
the first phase of street construction of the four-lane extension of the
east/west segment of Martin Luther King Jr. Parkway across the Des Moines River
to SE 14th Street (US 65/69), and includes construction of the Southeast
Connector from SE 4th Street to SE 9th Street except for the intersection at SE
6th Street which must be phased to maintain traffic in the area. The City of
FISCAL
IMPACT:
Amount: $3,750,000 City Engineer's Estimate
Funding
Source: 2008-2009 CIP, Page
Street-37, Southeast Connector -
ADDITIONAL
INFORMATION:
On March 7, 2005, by Roll Call 05-530, the City Council approved execution of an
Iowa Department of Transportation (IDOT) Agreement for the Southeast Connector; and by Roll Call 05-531, the City Council
approved the professional services agreement with Kirkham Michael &
Associates, (Roger Helgoth, President, Omaha, NE). In cooperation with City staff,
the consultant team has completed design of the Southeast Connector Paving
improvements from
The
Engineering Department has prepared plans, specifications, form of contract
documents, and City Engineer’s estimate for the construction of the Southeast
Connector Paving -
The
estimated construction cost is $3,750,000.
The proposed plans, specifications, and form of contract documents are
available for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date: March 7, 2005
Roll Call Number: 05-530
Action: Approving items regarding Southeast
Connector Project: Execution of Iowa Department of Transportation Agreement. (Council Communication No. 05-098) Moved by Hensley to adopt. Motion Carried 7-0.
Date: March 7, 2005
Roll
Call Number: 05-531
Action: Approving items regarding Southeast
Connector Project: Execution of Professional Services Agreement with Kirkham
Michael & Associates, (Dale Miller, President,
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Anticipated
actions include public hearing, receive and file bids, designate lowest bidder,
and approve contract and bond; also partial payments to the contractor and
final acceptance of work.
For more information on this
and other agenda items, please call the City Clerk’s Office at 515-283-4209 or
visit the Clerk’s Office on the second floor of City Hall, 400 Robert D Ray
Drive. Council agendas are available to
the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s
Council meeting. Citizens can also
request to receive meeting notices and agendas by email by calling the Clerk’s
Office or sending their request via email to cityclerk@dmgov.org.