Date
|
March 9, 2009
|
||
|
Agenda
Item No. 9 Roll
Call No. 09- Communication No.
09-137 Submitted by: Jeb E. Brewer, P.E. City
Engineer |
||||
AGENDA HEADING:
Approving Change Order No. 6 with Christensen Bros., Inc., for
additional work on the S.W. 9th Street Viaduct over M.L. King Jr. Parkway
Rehabilitation project, in an amount not to exceed $94,116.10.
SYNOPSIS:
Recommend
approval of Change Order No. 6 in an amount not to exceed $94,116.10 with Christensen Bros., Inc., Scott
Christensen, President, 644 River Road, P.O. Box 478, Cherokee, Iowa 51012, for additional bridge floor repair,
curb repair, parapet wall repair, diaphragm replacement, drain scupper repair,
and drain pipe fabrication.
FISCAL IMPACT:
Amount: $94,116.10
Funding
Source: 2009-10 CIP, Page Bridge 17, SW 9th
Street Viaduct over M.L. King Jr., Parkway BRV034, various funding being:
ADDITIONAL INFORMATION:
The
contract for the rehabilitation of the S.W.
9th Street Viaduct over M.L. King Jr. Parkway Rehabilitation project was awarded to Christensen Bros., Inc., in the amount
of $1,327,654, which was $132,017.20 under the original engineer’s estimate of
$1,459,671.20.
The S.W. 9th Street
Viaduct over M.L. King Jr. Parkway Rehabilitation project was designed to
restore the structural integrity to the structure. During construction, the amount of deterioration
was found to be more than had been estimated during the design of the
project. This change order adjusts the
estimated quantities for bridge floor repair, curb repair, and parapet wall
repair. The change order also adds
replacement of diaphragms that were too deteriorated to repair, repair of seven
drain scuppers that were badly corroded, and drain pipe fabrication to repair
corrosion and freeze damage. This
project was bid using the Iowa Department of Transportation (IDOT)
specifications, which require field measurements of bridge repair items,
because the quantities must be determined during removal operations. The $94,116.10 cost of this change order
adjusts final contract quantities for these items to as-built quantities.
PREVIOUS COUNCIL ACTION(S):
Date: December
6, 2004
Roll
Call No. 04-2657
Action: On SW 9th Street
Viaduct over M.L. King, Jr. Parkway and Railroad Bridge Rehabilitation:
Resolution approving plans, specifications, form of contract documents,
Engineers estimate and designating lowest responsible bidder as Christensen
Bros., Inc. (Scott Christensen, President), $1,327,654. Moved by Hensley to adopt. Motion Carried 7-0
Date: December 6,
2004
Roll
Call No. 04-2658
Action: Approving
contract and bond and permission to sublet. Moved by Hensley to adopt. Motion Carried 7-0
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE
COMMITMENTS:
Normal
actions for award of the construction contract for the work.
For more information on this and other agenda items,
please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office
on the second floor of City Hall, 400 Robert D. Ray Drive. Council agendas are available to the public
at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council
meeting. Citizens can also request to
receive meeting notices and agendas by email by calling the Clerk’s Office or
sending their request via email to cityclerk@dmgov.org.