Ordering
construction of the following: High
Street Realignment - 10th Street to 14th Street - Phase 2 - Receiving bids,
(3-24-09), and Setting date of hearing, (4-6-09). (Construction Estimate -
$680,000).
SYNOPSIS:
Recommend
the City Council proceed with construction of this improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below. As one of the conditions of the Urban
Renewal Development Agreement with Wellmark, Inc. for Wellmark's
new corporate headquarters, the City is required to construct a major
realignment of High Street to allow for a more efficient design of the Wellmark
corporate headquarters and parking garage.
Construction of the Phase 1 of the High Street alignment began in August
2008. This project is the second phase
of the High Street Alignment.
FISCAL
IMPACT:
Amount: $680,000 City Engineer's Estimate
Funding
Source: 2009-2010 CIP, Page
Street-17, High Street Realignment - 10th Street to 14th Street, STR204 being 50%
in RISE funds, $340,000, and 50% from Polk County, $340,000
ADDITIONAL
INFORMATION:
On April 21, 2008, by Roll Call
No. 08-715, the City Council approved an Urban Renewal Development Agreement
with Wellmark, Inc. for the redevelopment of the three block area bounded by
The planned relocation of High Street between 10th
and 14th Streets must be completed to create the parcels needed by Wellmark for
the new office building and garage/multi-use building.
The Polk County Board of Supervisors agreed to
assist the City in the retention of Wellmark's home
office facilities and the associated employment opportunities by making a grant
to the City for the relocation of High Street, which was approved by the City Council
on May 5, 2008, under Roll Call No, 08-276.
On May 19, 2008, under Roll Call
No, 08-310, the City Council
approved an Iowa Department of
Transportation RISE agreement for
High Street Improvements funding. This RISE grant is for 50 percent of the total
cost of eligible project costs, up to a maximum amount of $2,588,456.
The
Engineering Department has prepared plans, specifications, form of contract
documents, and City Engineer’s estimate for the construction of the High Street
Realignment - 10th Street to 14th Street - Phase 2, 06-2008-008. The improvement includes pavement removal and
replacement, sidewalk removal and replacement, excavation, storm sewer, water
main relocation, traffic signals, pavement markings, construction survey,
sodding and site restoration, all accordance with the contract documents
including Plan File Nos. 496-88/128, on High Street from
The
estimated construction cost is $680,000.
The proposed plans, specifications, and form of contract documents are
available for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date: July 28, 2008
Roll
Call Number: 08-1361
Action: On
bidder as Sternquist Construction, Inc., (Britt Sternquist,
President), $677,698.70. (Council Communication No. 08-443) Moved by Hensley to adopt.
Motion Carried 7-0.
Action: Letter
of Agreement with
Action: Items regarding Wellmark Urban Renewal
Development Agreement: (Council
Communication No. 08-217)
(A) Hearing
on proposed Urban Renewal Development Agreement with Wellmark, Inc., and
vacation and conveyance of property in the three-block area bounded by High
Street, Grand Avenue, 11th Street and 14th Street,
$1,586,000. Moved by Hensley to
adopt. Motion Carried 7-0.
BOARD/COMMISSION