Date
|
March 23,
2009
|
||
|
Agenda
Item No. 6 Roll
Call No. 09- Communication No.
09-171 Submitted by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA HEADING:
Approving
and authorizing the execution of Iowa Department of Transportation Addendum to
the Predesign Agreement for Merle Hay Road (Iowa 28) Widening at Urbandale
Avenue.
SYNOPSIS:
Recommend approval of the
Addendum to the Predesign Agreement with the Iowa Department of Transportation
(Iowa DOT) for Merle Hay Road (Iowa 28) Widening at Urbandale Avenue. The project provides for the installation of
left-turn lanes on Merle Hay Road at Urbandale Avenue.
FISCAL IMPACT:
Amount: $2,360,000 (original estimate $2,000,000)
Funding Source:
Various funding being:
ADDITIONAL INFORMATION:
The proposed improvement consists of widening the
north and south approaches on Merle Hay Road in order to provide left turn
lanes. The current pavement width of 49’
would be widened to 65’. A raised median
would be installed on Merle Hay Road within the vicinity of the
intersection. New traffic signals with
backplates would also be installed, including north-south left turn
phasing. A 10’ clear zone would be
established within the limits of the project.
This intersection ranked 55th on the state’s 2001-2005
“Statewide Intersection Candidate Listing.”
Due to its high crash experience, this location was previously reviewed
in a study that was commissioned by the Iowa DOT Traffic Safety Office.
On March 24, 2008, by Roll Call No. 08-464, the City
Council approved the Predesign Agreement for Merle Hay Road (Iowa 28) Widening
at Urbandale Avenue. The predesign agreement
authorized the City to perform the survey, design, environmental clearance, and
right-of-way acquisition phases of the project.
City staff has completed the survey, preliminary design, and
environmental clearance phases of the project, including an updated cost
estimate. On January 29, 2009, a public
informational meeting for the project was held at Hillis Elementary School.
The total project cost for the widening project was
originally estimated to be $2,000,000. The
updated cost estimate for the project, based on preliminary design, is
$2,360,000. $750,000 in Highway Safety
Improvement Program funding, $400,000
in Iowa Clean Air Attainment Program funding, and $500,000 in Traffic Safety
Improvement Program funding have been approved for this project. The remaining costs will be split between the
Iowa Department of Transportation (55%) and the City of Des Moines (45%). This addendum to the Predesign Agreement
increases the estimated project cost and identifies the various funding sources
to be utilized to complete the project. Construction of this project by the Iowa DOT
is anticipated in 2010.
PREVIOUS
COUNCIL ACTION(S):
Date: March 24, 2008
Roll Call Number: 08-464
Action: Approving execution of Iowa Department of Transportation (IDOT)
Predesign Agreement for Merle Hay Road (Iowa 28) Widening at Urbandale
Avenue. (Council Communication No. 08-158) Moved by Coleman to adopt. Motion Carried 7-0.
Date: August 6, 2007
Roll Call Number: 07-1486
Action: Iowa Clean Air Attainment Program (ICAAP) Fund Applications to the Iowa Department of Transportation (IDOT) for Merle Hay Road and Urbandale Avenue Intersection Improvements, and SE 14th Street and East Indianola Avenue Intersection Improvements. (Council Communication No. 07-477
) Moved by Vlassis to adopt. Motion Carried 7-0.BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Normal
actions for award of the construction contract for the work.