Approving
and authorizing the execution of Iowa Department of Transportation Agreement
for S.E. 5th Street
Resurfacing from E. Army Post Road
to E. County Line Road.
SYNOPSIS:
Recommend
approval of the Iowa Department of Transportation (IDOT) Agreement No.
01-09-ESP-028 for Federal Stimulus project funding for S.E. 5th Street Resurfacing
from E. Army Post Road
to E. County Line Road. Federal Stimulus funds up to a maximum amount
of $580,000 are available for 100% of construction costs. The City’s portion of the project, consisting
of the design, inspection, and construction administration, is estimated to be
$75,000.
FISCAL IMPACT:
Amount: $655,000
Funding Source: Various
funding sources as follows:
- $580,000 Federal Stimulus
Funds
- $75,000 2009-10 CIP, Page
Street-32, Rehabilitation and Preservation of Major Roadways, STR222, G.O.
Bonds; with a $75,000 transfer from 2009-10 CIP, Page Street-23,
McKinley Avenue Widening – Fleur Drive to E. Indianola Avenue,
STR212, G.O. Bonds
ADDITIONAL
INFORMATION:
A number of transportation related projects were
submitted to and approved by the Des Moines Area Metropolitan Planning
Organization Executive Committee at their January 29, 2009 meeting for funding
under the American Recovery and Reinvestment Act of 2009. The funding request for S.E.
5th Street Resurfacing from E. Army Post Road
to E. County Line Road
was approved, and IDOT has prepared an
agreement for the proposed improvement, which consists of base repair and
preparation of the existing roadway and resurfacing with hot mix
asphalt. This project will be constructed
in the summer of 2009. The receipt of
this and other transportation stimulus funds has allowed an acceleration of
street projects. The local share of
transportation stimulus funds must be funded out of existing street CIP
funds. The STR222 account requires a transfer
of $75,000 from STR212, McKinley Avenue Widening, to cover anticipated local
costs. Sufficient funds are available in
STR212 as it also received stimulus funds.
PREVIOUS COUNCIL ACTION(S): NONE
BOARD/COMMISSION ACTION(S): NONE
ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:
Normal Council actions on consultant
services for design and construction administration, and construction
contracts.
For more information on this and other agenda items,
please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office
on the second floor of City Hall, 400
Robert D. Ray Drive. Council agendas are available to the public
at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council
meeting. Citizens can also request to receive meeting notices and agendas by
email by calling the Clerk’s Office or sending their request via email to
cityclerk@dmgov.org.