Approving and authorizing the execution of Iowa Department of Transportation Agreement for Principal Riverwalk – Walnut/Grand Avenue West.

 

 

SYNOPSIS:

 

Recommend approval of Iowa Department of Transportation (IDOT) Agreement No. OSP-09-ESP-10 for Federal Stimulus project funding for Principal Riverwalk – Walnut/Grand Avenue West.  Federal Stimulus funds up to a maximum amount of $2,526,235 are available for construction costs.  State Recreational Trail funding will be used to fund the remaining construction costs.  The City’s portion of the project, consisting of the project administration, is estimated to be $50,000.

 

 

FISCAL IMPACT:

 

Amount:  $2,850,000

 

Funding Source:  Various funding sources as follows:

 

  • $2,526,235 Federal Stimulus Funds
  • 2009-10 CIP, Page Park Improvements - 23, Principal Riverwalk, PKS162, Being: $273,765 in State Recreational Trails funding and $50,000 in Vision Iowa

 

 

ADDITIONAL INFORMATION:

 

A number of transportation related projects were submitted to and approved by the Des Moines Area Metropolitan Planning Organization (MPO) Executive Committee at their January 29, 2009 meeting for funding under the American Recovery and Reinvestment Act (ARRA) of 2009.  The IDOT also requested submittal of recreational trails projects for possible ARRA funding.  The funding request for Principal Riverwalk was approved by both the MPO and IDOT.  The MPO allocated $1,653,000 and the IDOT allocated $873,235.  The two allocations are being combined with State Recreational Trail funding to construct the west side of the Principal Riverwalk between Walnut Street and Grand Avenue.  The IDOT has prepared an agreement for the proposed improvement. 

 

This project will include construction on the river side of the levee on both blocks and the plaza on the land side between Walnut Street and Locust Street in front of the Old Library.  The project construction includes the multi-purpose trail, floodwall, irrigation and lighting, plaza and promenade pavers.  Construction of this project will begin in the fall of 2009 and will be completed within one year.  Construction of the plaza and promenade adjacent to the YMCA will be deferred, pending the proposed redevelopment of that property. 

 

 

PREVIOUS COUNCIL ACTION(S):  

 

Date:  April 6, 2009

 

Roll Call Number:  09-520

 

Action:  Approving Professional Services Agreement with Stanley Consultants, Inc. for the following Principal Riverwalk items:  (A) Design and construction phase services for Principal Riverwalk Walnut to Grand-West, not to exceed $325,333.17.  (Council Communication No. 09-205)  Moved by Hensley to adopt.  Motion Carried 7-0. 

 

Date:  October 27, 2008

 

Roll Call Number:  08-1830

 

Action:  Approving execution of Iowa Department of Transportation Grant Agreement for the Principal Riverwalk Kiosk and Trail.  (Council Communication No.

  08-644)  Moved by Vlassis to adopt.  Motion Carried 7-0.

Date:  November 19, 2007

 

Roll Call Number:  07-2267

 

Action:  Project Cooperation Agreement with Department of the Army for construction of Phase I of the Principal Riverwalk and approving agreement with Principal Life Insurance Company and The Des Moines River Front Development Authority for responsibility of Non-Federal Sponsor financial obligations and work related to the Principal Riverwalk.  (Council Communication No. 07-680)  Moved by Hensley to adopt.  Motion Carried 7-0.

 

Date:  October 24, 2005

 

Roll Call Number:  05-2600

 

Action:  Vision Iowa Program Grant Award Agreement for the construction of the Rediscovering the Rivers Project including the Principal Riverwalk and Meredith Riverpoint Trail.  (Council Communication No. 05-596)  Moved by Hensley to adopt.  Motion Carried 7-0.

 

BOARD/COMMISSION ACTION(S): NONE

 

 

ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:

 

Normal Council actions on consultant services for design and construction administration, and construction contracts.

 

 

For more information on this and other agenda items, please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall, 400 Robert D. Ray Drive.  Council agendas are available to the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council meeting.  Citizens can also request to receive meeting notices and agendas by email by calling the Clerk’s Office or sending their request via email to cityclerk@dmgov.org.