|
||||
|
Date
|
May 5, 2009
|
||
|
Agenda
Item No. 10 Roll
Call No. 09- Communication No.
09-272 Submitted by: Jeb E. Brewer, P.E. City
Engineer |
||||
AGENDA HEADING:
Resolution
approving request for changes in contract completion provisions on High Street
Realignment - 10th Street to 14th Street - Phase 2.
SYNOPSIS:
Recommend approval of request from Corell
Contractors, Inc., Grant Corell, President, 1300 Lincoln Street,
West Des Moines, Iowa, 50265, for changes in the completion provisions of the
contract to change the late start date from April 20, 2009 to June 29, 2009,
and to reduce the working days from 70 working days to 60 working days.
FISCAL IMPACT:
Amount: $0.00
Funding Source: 2009-2010 CIP, Page Street-17, High Street Realignment – 10th
Street to 14th Street, STR204, being 50% in
RISE funds and 50% from Polk County.
ADDITIONAL INFORMATION:
When
the construction contract for the High Street Realignment - 10th
Street to 14th Street - Phase 2 project was being assembled, the
Engineering Department consulted and coordinated with Wellmark and their
contractor to determine what completion provisions were required in the City’s
contract to allow both projects to proceed simultaneously. Due to changes in the Wellmark project schedule,
Wellmark and Corell Contractors, Inc. have requested that work on the City’s
contract not begin until June 29, 2009, to facilitate work on the Wellmark
site. This change in the start date of
the City’s contract along with the reduction in working days should allow the
project to be completed this fall.
PREVIOUS COUNCIL ACTION(S):
Date:
April 6, 2009
Roll Call Number: 09-590
Action: Approval of contract
and bond and permission to sublet. Moved by Hensley to
adopt. Motion Carried 6-1. Absent:
Meyer.
Date:
April 6, 2009
Roll Call Number: 09-589
Action: On High Street Realignment – 10th Street to 14th Street – Phase 2: Resolution approving plans, specifications, form of contract documents, Engineer’s Estimate and designating lowest responsible bidder as Corell Contractor, Inc., (Grant S. Corell, President), $621,276.38. (Council Communication No. 09-202
) Moved by Hensley to adopt. Motion Carried 6-1. Absent: Meyer.BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS: