Agenda Item No. 7D Roll Call No. 09- Communication
No. 09-384 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA
HEADING:
Ordering
construction of the following: Southeast
Connector Paving -
SYNOPSIS:
Recommend
the City Council proceed with construction of this improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below. This
project provides for the construction of the four-lane extension of the
east/west segment of
FISCAL
IMPACT:
Amount: $7,191,200 City Engineer's Estimate
Funding Source:
2009-2010 CIP, Page Street-35, Southeast Connector - S.W.
Second to
·
$2,300,000 in Federal Transportation IA116, IA122, and IA080 Funds
for up to 80% eligible construction with
$3,402,015.39 in Des Moines Tax Increment Bonds for the Local match on Division
1 work from SW 2nd - SE 6th Streets
funded under STR214, Page Street-35 with a transfer of $2,000,000 in Des Moines Tax Increment Bonds from STR219,
Page Street-36, Southeast Connector – S.E. Sixth to S.E 14th;
·
$1,284,764.61 in Federal Transportation FY09 Section 125 Earmark
Funds for 100% eligible construction on Division 2 work on SE 6th Street; and
·
$204,420.00 from Des Moines Water Works for Division 3 water main
construction not Federal eligible.
ADDITIONAL
INFORMATION:
On
March 7, 2005, by Roll Call 05-530, the City Council approved execution of an
Iowa Department of an IDOT Agreement
for the Southeast Connector; and by Roll Call 05-531, the City Council approved
the professional services agreement with Kirkham Michael &
Associates, (Roger Helgoth, President,
The
Engineering Department has prepared plans, specifications, form of contract
documents, and City Engineer’s estimate for the construction of the Southeast
Connector Paving -
The
proposed plans, specifications, and form of contract documents are available
for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date: March 9, 2009
Roll Call Number: 09-421
Action: On Southeast
Connector Paving – SE 4th Street to SE 9th Street:
Resolution approving plans, specifications, form of contract documents,
Engineer’s Estimate and designating lowest responsible bidder as Elder
Corporation, (Jared Elder, President), $3,356,000. (Council
Communication No. 09-156) Moved by Meyer to adopt. Motion Carried 6-1. Absent: Cownie.
Date: March 9, 2009
Roll Call Number: 09-422
Action: (A) Approving contract and bond and permission
to sublet. Moved by Meyer to
adopt. Motion Carried 7-0.
Date: March 7, 2005
Roll
Call Number: 05-530
Action: Approving items regarding Southeast
Connector Project: Execution of Iowa Department of Transportation
Agreement. (Council Communication No. 05-098) Moved by Hensley to adopt. Motion Carried 7-0.
BOARD/COMMISSION ACTION(S):
Date: March 18, 2009
Roll Call Number: N/A
Action: The Access Advisory Board recommended
approval of the Southeast Connector from SW 2nd to SE 9th
Streets, including streets, sidewalks, and trails.
Date: February 17, 2009
Roll Call Number: N/A
Action: Urban Design Review Board recommended
approval of the final design for the SE Connector from SW 2nd to
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Anticipated
actions include public hearing, receive and file bids, designate lowest bidder,
and approve contract and bond; also partial payments to the contractor and
final acceptance of work.