Council |
Date |
July
27, 2009 |
||
|
Agenda Item No. 6B Roll Call No. 09- Communication
No. 09-531 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA
HEADING:
Ordering
construction of the following:
Riverpoint West Street Improvements - Receiving bids, (8-11-09), and
Setting date of hearing, (8-24-09). (Construction Estimate - $2,777,254.35).
SYNOPSIS:
Recommend
the City Council proceed with construction of this improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below.
The City is working with River Point West LLC (George Sherman,
President, 233 Park Avenue South, Suite 201,
Minneapolis, MN) and Hubbell Realty Company (Rick Tollakson, President, 6900
Westown Parkway, West Des Moines, IA) for redevelopment of Riverpoint West and
the former Pittsburgh Des Moines Steel site, respectively. The parties agreed to undertake the extension
of SW 11th Street from Tuttle Street to Dart Way and Murphy Street from SW 9th
Street to SW 11th Street. This project
includes reconstructing existing roadways and constructing new roadways in the
eastern portion of the Riverpoint West redevelopment area. SW 11th Street will be reconstructed from ML
King Jr. Parkway to Tuttle Street and a new roadway extended from Tuttle Street
to Dart Way. A new Murphy Street will be
constructed from SW 11th Street to SW 9th Street to accommodate the improved
grade on SW 11th Street. This project
will include grading, pavement, storm sewers & intakes, sanitary sewers,
water main.
FISCAL
IMPACT:
Amount: $2,777,254.35 City Engineer's Estimate
Funding Source: 2009-2010 CIP, Page Street-35, Riverpoint
West Street Improvements, STR227, TIF-Backed G. O. Bonds, being:
• $536,147.43 in City of Des
Moines TIF-Backed G. O. Bonds from STR227.
• $521,290 in Iowa Department of Transportation
Revitalize Iowa's Sound Economy (RISE) funds for 50% of construction cost of
eligible items with $521,290 maximum. (Division 1 Paving items are RISE
eligible.)
• $1,719,816.92 in private contributions in
accordance with the Supplemental Development Agreement approved on May 19,
2008, under Roll Call No. 08-935, being:
o
$1,308,006.24 from Riverpoint West L.L.C., which contains proceeds
from the HUD Section 108 Loan approved by the City Council on July 23, 2007,
under Roll Call No.07-1456, and is to be paid within 10 days after award of the
contract.
o
$411,810.68 from Hubbell
Terminal Corporation, which shall be paid at completion of the project.
ADDITIONAL
INFORMATION:
Under separate development agreements, the City is
working with River Point West LLC (George Sherman, President,
By a Preliminary Agreement approved on May 23, 2005,
by Roll Call 05-1331, the parties contemplated the extension of SW 11th Street
from Tuttle Street to Dart Way and Murphy Street from SW 9th Street to SW 11th
Street, but there was no agreement executed by all parties addressing the
issues involved in the design, construction and payment for the work. On May 19, 2008, by Roll Call 08-935, the
City Council approved a Supplemental Development Agreement to undertake such
design, construction, and payment in a uniform and consistent way. The Supplemental Development Agreement also
provided for the conveyance of Hubbell-owned property to the City of Des Moines
for right-of-way improvements on SW 11th Street and Murphy Street.
The
Engineering Department and River Point West LLC have jointly
worked with the same consultant,
Snyder & Associates (David Moeller, President), 2727 S.W. Snyder
Blvd., Ankeny, IA, 50023, to prepare plans,
specifications, form of contract documents, and City Engineer’s estimate for
the construction of the Riverpoint West Street Improvements, 06-2007-010. The improvement includes reconstructing
existing roadways and constructing new roadways in the eastern portion of the Riverpoint West redevelopment area. SW 11th Street will be reconstructed
from ML King Jr. Parkway to Tuttle Street and a new roadway extended from
Tuttle Street to Dart Way. A new Murphy
Street will be constructed from SW 11th Street to SW 9th Street to accommodate
the improved grade on SW 11th Street.
This project will include grading, pavement, storm sewers & intakes,
sanitary sewers, water main, and other incidental items; in accordance with the
contract documents, including Plans File Nos. 493-001/106.
The
proposed plans, specifications, and form of contract documents are available
for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date: May 19, 2008
Roll Call Number: 08-935
Action: Supplemental Development Agreement with River Point West
LLC, Hubbell Realty Company and Hubbell Terminal Corporation for construction
of SW 11th and Murphy Street
improvements in conjunction with Riverpoint West and former Pittsburgh DSM
Steel redevelopment projects. (Council
Communication No. 08-304) Moved by Hensley to adopt. Motion Carried 7-0.
Date: October 8, 2007
Roll Call Number: 07-1991
Action: Amended and Restated Urban Renewal
Development Agreement with River Point West LLC and a Loan Agreement with River
Point West Investment Fund LLC for the Riverpoint West Redevelopment Project. (Council Communication No. 07-612) Moved by Hensley to adopt. City Manager will provide
periodic status reports to Council. Motion Carried 7-0.
Date: July 23, 2007
Roll Call Number: 07-1456
Action:
Resolutions regarding to the Riverpoint West Redevelopment Project:
(C) Resolution approving form and authorizing
execution and delivery. Moved by Hensley to adopt. Motion Carried 7-0.
Date: February 26, 2007
Roll Call Number: 07-355
Action: Revitalize Iowa’s Sound Economy (RISE)
Grant Agreement to construct and reconstruct a roadway in the Riverpoint West
Area (SW 11th Street from Martin Luther King, Jr. Parkway to Dart
Way). (Council Communication No. 07-092) Moved by Hensley to adopt. Motion Carried 6-1.
Date: November 21, 2005
Roll Call Number: 05-2793
Action: Urban Renewal Development Agreement and Brownfields Cleanup Revolving Loan Fund (“BCRLF”) Agreement
with Hubbell Realty Company and Hubbell Terminal Corporation for the
redevelopment of a portion of the Riverpoint West area. (Council Communication No. 05-674) Moved by Hensley to adopt. Motion Carried 7-0.
Date: May 23, 2005
Roll Call Number: 05-1331
Action: Preliminary Agreement with Hubbell Realty Company and Hubbell Terminal Corporation (Rick Tollakson, President & CEO) and Riverpoint West LLC (George Sherman, President) for redevelopment of parcels west of SW 9th along Tuttle and Murphy Streets. (Council Communication No. 05-305
) Moved by Hensley to adopt. Motion Carried 6-1. Absent:Vlassis.BOARD/COMMISSION
ACTION(S): NONE