Ordering construction of the following:  7th & Grand Parking Garage Rehabilitation - Receiving bids, (9-29-09), and Setting date of hearing, (10-12-09).  (Construction Estimate - $503,315).

 

 

SYNOPSIS:

 

Recommend the City Council proceed with construction of the improvement and set dates to receive bids and hold a public hearing, as required by Iowa Code, utilizing the method of financing referenced below.  This project provides for structural repair and rehabilitation at three parking garages (7th & Grand, 4th & Grand, and 3rd & Court) to address deterioration that has occurred.  This work is necessary to preserve the City’s investment in these parking structures and restore their structural integrity. 

 

 

FISCAL IMPACT:

 

Amount:  $503,315 (City Engineer's Estimate)

 

Funding Source:  2009-2010 CIP, Page PKG-5, Parking Facility Rehab/Repair Program, PKG016, Parking System Revenue

 

 

ADDITIONAL INFORMATION:

 

The Engineering Department has prepared plans, specifications, form of contract documents, and City Engineer’s estimate for the construction of the 7th & Grand Parking Garage Rehabilitation, 04-2010-003.  The improvement includes concrete stair repair, stair nosing repairs, rail post support repair, floor drain repairs, tee beam stem repair, beam repair, column repair, bottom tee repair, epoxy crack injection, crack sealing, cove sealant, traffic paint, carbon fiber reinforcing (furnish), carbon fiber reinforcing (installation), temporary shoring, tee connection repair, reinforcing steel epoxy coated, traffic control, grind concrete surface at level 6.5, angle support, concrete removal, concrete replacement, steel handrail galvanized, storefront and mobilization in accordance with the contract documents, including Plan Files 508-055/081 at the City of Des Moines 7th & Grand Parking Garage, and also includes minor repair work at the 4th & Grand and 3rd & Court Parking Garages, Des Moines, Iowa.

 

The estimated construction cost is $503,315.  The proposed plans, specifications, and form of contract documents are available for public inspection in the City Engineer's Office.

 

 

PREVIOUS COUNCIL ACTION(S):  NONE

 

 

BOARD/COMMISSION ACTION(S):  NONE

 

 

ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:

 

Anticipated actions include public hearing, receive and file bids, designate lowest bidder, and approve contract and bond; also partial payments to the contractor and final acceptance of work.

 

 

For more information on this and other agenda items, please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall, 400 Robert D. Ray Drive.  Council agendas are available to the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council meeting.  Citizens can also request to receive meeting notices and agendas by email by calling the Clerk’s Office or sending their request via email to cityclerk@dmgov.org.