Council
CommunicationOffice
of the City Manager

 
NewCityLogo-August2008 

Date

November 9, 2009

 

Agenda Item No.       6A

Roll Call No.              09-

Communication No.  09-787

Submitted by:  Jeb E. Brewer, P.E.

                         City Engineer

 

 

AGENDA HEADING:

 

Ordering construction of the following:  Court Avenue & Water Street Gatewell and River Outlet - Receiving bids, (11-24-09), and Setting date of hearing, (12-7-09).  (Construction Estimate - $537,790).

 

 

SYNOPSIS:

 

Recommend the City Council proceed with construction of the improvement and set dates to receive bids and hold a public hearing, as required by Iowa Code, utilizing the method of financing referenced below.  This project is the first phase of the Court Avenue & Water Street Sewer Separation project, which will construct a separate storm sewer system and storm water pump station to serve this area.  This area of downtown is currently served by a combined (storm and sanitary) sewer system, resulting in localized flooding during heavy rain events, especially during high river levels.  The Court Avenue & Water Street Gatewell and River Outlet will construct the required gatewell at the levee and the outlet to the river.  Future projects will construct the pump station and the storm sewer system to convey storm water to the new outlet to the river.

 

 

FISCAL IMPACT:

 

Amount:  $537,790 City Engineer's Estimate

 

Funding Source:  2009-2010 CIP, Page Storm-6, Court Avenue/Water Street Sewer Separation, STE081, Storm Water Utility Revenue Bonds to be issued.

 

 

ADDITIONAL INFORMATION:

 

The Engineering Department has prepared plans, specifications, form of contract documents and City Engineer’s estimate for the construction of the Court Avenue & Water Street Gatewell and River Outlet, 08-2010-006.  The improvement includes construction of a storm water pump station gatewell and outlet structure, 72" diameter storm sewer, sheet pile construction and miscellaneous associated work including cleanup and other incidental items; in accordance with the contract documents, including Plans File Nos. 509-008/014, south of Court Avenue and east of Water Street along the west Des Moines River Levee in downtown Des Moines, Iowa.

 

The estimated construction cost is $537,790.  The proposed plans, specifications and form of contract documents are available for public inspection in the City Engineer's Office.

 

 

PREVIOUS COUNCIL ACTION(S): 

 

Date:  October 27, 2008

 

Roll Call Number:  08-1874 

 

Action:  Approving Professional Services Agreement with Veenstra & Kimm, Inc. for design and construction phase services for the Court Avenue-Water Street Sewer Separation Project, not to exceed $595,712.  (Council Communication No.  08-646)  Moved by Hensley to adopt.  Motion Carried 7-0.

 

 

BOARD/COMMISSION ACTION(S):  NONE

 

 

ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:

 

Anticipated actions include public hearing, receive and file bids, designate lowest bidder and approve contract and bond; also, partial payments to the contractor and final acceptance of work.

 

 

 

 

For more information on this and other agenda items, please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall, 400 Robert D. Ray Drive.  Council agendas are available to the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council meeting.  Citizens can also request to receive meeting notices and agendas by email by calling the Clerk’s Office or sending their request via email to cityclerk@dmgov.org.