Agenda Item No. 53 Roll Call No. 09- Communication
No. 09-796 Submitted
by: Jeb E. Brewer, P.E. City Engineer
|
||||
AGENDA
HEADING:
Hearing
on Livingston Avenue Storm Sewer Televising:
Resolution approving plans, specifications, form of contract documents,
engineer’s estimate, receive and file bids and designating lowest responsible
bidder as Priority Excavating LLC, Toby Torstenson,
President, 773 NE 47th Place, Des Moines, IA 50313, $251,000.
SYNOPSIS:
This
is a public hearing to allow for public input on the Livingston Avenue Storm
Sewer Televising and take the necessary actions as required by Iowa Code to
authorize a contract for construction of the proposed project. In the summer of 2008, there was extensive
damage across Iowa from flooding and other severe weather. The Iowa Department of Economic Development
IDED) has awarded the City of Des Moines a grant under the Infrastructure
Assistance program, as part of the Federal Disaster Relief program
under the Jumpstart Program for Housing Assistance, Small Business Assistance
and Infrastructure Assistance. The
lining of the Livingston Avenue Storm Sewer System will be accomplished using
two separate contracts. The first
contract being presented under this roll call is the cleaning and
televising. The second contract to be
funded from the grant will be the actual lining.
FISCAL
IMPACT:
Amount: $251,000 Construction Contract ($342,250 City
Engineer's Estimate)
Funding
Source: Livingston Avenue Sewer
Lining, STE085, Being: $251,000 in HUD Disaster funds
from the IDED for 100% of construction costs associated with the lining of the
Livingston Avenue Storm Sewer System with a $2,000,000 maximum in Federal
Jumpstart Infrastructure Assistance funds.
ADDITIONAL
INFORMATION:
In
the summer of 2008, there was extensive damage across
On
February 9, 2009, under Roll Call Number 09-230, the City Council authorized
submittal of four project applications under the Infrastructure Assistance
Program. The projects were identified as
those being the most competitive in the grant selection criteria. Important criteria considered were the direct
relationship of the project to the 2008 disaster, threat to health, safety or
welfare, benefit to low and moderate income persons and burden associated to
the same group if local revenue was used to accomplish the project and the
ability to construct the projects quickly.
The four project applications submitted were as follows:
The
design and construction phase services for these proposed projects will be paid
with sanitary and storm water utility fees.
Three of the
four projects submitted were selected for funding, and the City of
Des Moines has received contracts from the IDED for the following:
·
Contract
Number 08-DRI-005 in the amount of $2,500,000 for Five Storm Water Pump
Stations in the Birdland and Central Place Areas,
·
Contract
Number 08-DRI-006 in the amount of $2,000,000 for Livingston Avenue Storm Sewer
System Lining,
·
Contract
Number 08-DRI-007 in the amount of $1,200,000 for Lining of the Sanitary Sewers
in the Eastern Portion of the Highland Hills Sanitary Sewer Subsystem.
These
three grants were approved by the City Council on May 18, 2009, under Roll Call
No. 09-832.
The
lining of the Livingston Avenue Storm Sewer System will be accomplished using
two separate contracts. The first
contract being presented is the cleaning and televising of the sewers. The second contract to be funded from the
grant will be the actual lining.
On
October 12, 2009, under Roll Call No. 09-1829, the City Council received and
filed plans, specifications, form of contract documents and City Engineer's
estimate for the construction of the Livingston Avenue Storm Sewer
Televising. Before the City Council can
enter into a contract, it must hold a public hearing and approve the proposed
plans, specifications, form of contract documents and engineer's estimate for
the construction of the Livingston Avenue Storm Sewer Televising, 08-2010-001. The improvement includes cleaning and
televising of approximately 23,000 lineal feet of 12" through 66"
storm sewer; all in accordance with the contract documents including Plan File
Nos. 508/-086/092 at an area bounded by S.W. 1st Street, the Des Moines River,
S.E. 9th Street and E. Columbus Avenue in Des Moines, Iowa.
Sealed
bids for said improvement were submitted by the following bidders:
Priority
Excavating LLC, Des Moines, IA
Mid-America
Pipe Services, LLC, Moscow Mills, MO
Visu-Sewer
Clean & Seal, Inc., Pewaukee, WI
Hydro-Klean,
Inc., Des Moines, IA, Bid not read
Municipal
Pipe Tool Co., Inc., Hudson, IA, Bid not read
The
bids were received and opened at a public meeting presided over by the City
Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray
Drive, Des Moines, Iowa at 11:00 a.m. on November 3, 2009.
The
City Engineer has determined that the lowest responsive, responsible bid for
the construction of said improvement was submitted by Priority Excavating LLC in
the amount of $251,000, and said bid should be accepted. The Finance Director has determined that funds
are available for said improvement, as stated above.
PREVIOUS
COUNCIL ACTION(S):
Date: October 12, 2009
Roll Call Number: 09-1829
Action: Ordering construction of the following: Livingston
Avenue Storm
Sewer Televising: Receiving of bids,
(10-27-09), and Setting date of hearing, (11-9-09). (Construction Estimate -
$342,250). (Council Communication No. 09-724) Moved by Mahaffey to adopt. Motion Carried 7-0.
Date: May 18, 2009
Roll Call Number: 09-832
Action: Approving execution of three (3) CDBG Disaster Recovery Infrastructure Grants with the Iowa Department of Economic Development. (Council Communication No.
09-338) Moved by Kiernan to adopt. Motion Carried 6-1. Absent: Cownie.Action:
Submission of four (4) CDBG Disaster Recovery
Infrastructure Applications to the Iowa Department of Economic
Development. (Council
Communication No. 09-063)
Moved by Kiernan to adopt. Motion
Carried 6-1. Absent: Cownie.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Partial
payments to the contractor and final acceptance of work.