Council |
Date |
|
||
|
Agenda Item No. 6C Roll Call No. 10- Communication
No. 10-032 Submitted
by: City Engineer |
||||
AGENDA
HEADING:
Ordering
construction of the following: E. 33rd
Street & Easton Boulevard Intersection Improvements - Receiving bids,
(2-9-10), and Setting date of hearing, (2-22-10). (Construction Estimate -
$490,000).
SYNOPSIS:
Recommend
the City Council proceed with construction of the improvement and set dates to
receive bids and hold a public hearing, as required by Iowa Code, utilizing the
method of financing referenced below. This
project provides for widening Easton Boulevard east and west of E. 33rd Street
in order to provide for left turn lanes.
E. 33rd Street will be restriped to provide left turn lanes approaching
Easton Boulevard. New traffic signals
will be installed at the intersection.
FISCAL
IMPACT:
Amount: $490,000 City Engineer's Estimate
Funding
Source: 2009-2010 CIP, Page
Street-15, E. 33rd and Easton Boulevard Intersection Improvements, STR234,
Being: $400,000 in Iowa DOT Traffic Safety Funds (Max $400,000) and 90,000 in
City G. O. Bonds
ADDITIONAL
INFORMATION:
The
Engineering Department has prepared plans, specifications, form of contract
documents, and City Engineer’s estimate for the construction of the E. 33rd
Street & Easton Boulevard Intersection Improvements, 06-2009-004. The improvement includes removing pavement
and existing traffic signal system and construction a Portland Cement Concrete
widening eight (8) inches thick with a Hot Mix Asphalt overlay, Portland Cement
Concrete reconstruction nine (9) inches thick, new traffic signal system, storm
sewer, subdrains, driveways, sidewalks, pavement markings, surface restoration
and other incidental items; in accordance with the contract documents,
including Plans File Nos. 514-164/195, at the intersection of E. 33rd Street
and Easton Boulevard and on Easton from E. 33rd Street to E. 34th Street, Des
Moines, Iowa.
The
estimated construction cost is $490,000.
The proposed plans, specifications, and form of contract documents are
available for public inspection in the City Engineer's Office.
PREVIOUS
COUNCIL ACTION(S):
Date:
Roll Call Number: 09-063
Action: Authorizing
execution of Iowa Department of Transportation Agreements for the following:
(C) E. 33rd Street and Easton
Boulevard intersection improvements. (Council Communication No. 09-030) Moved by Vlassis to
adopt. Motion Carried 7-0.
BOARD/COMMISSION
ACTION(S): NONE