Council
Communication
Office of the
City Manager
|
|
|
Date
|
January 25, 2010
|
|
Agenda Item No. 11A
Roll Call No. 10-
Communication
No. 10-035
Submitted
by: Jeb E. Brewer, P.E.
City Engineer
|
AGENDA HEADING:
Communication
from the City Manager recommending proposed street paving using special
assessments.
SYNOPSIS:
Recommend the City Council
proceed with proposed street paving improvements and set February 22, 2010, as the
date for the hearing on the proposed Resolution of Necessity, as required by
Iowa Code, before the City Council can proceed to utilize special assessments
against benefited property owners as part of the method of financing referenced
below. Property owners on the two
streets recommended for paving had previously submitted petitions to the City
Council requesting that the streets be paved.
Recommend the City Council authorize the City Engineer to proceed with
the actions necessary under the Iowa Code special assessment process and to
notify appropriate property owners.
FISCAL IMPACT:
Amount: $716,000, Total City
Engineer's Preliminary Estimate for assessment purposes with $140,743.31
assessed, $21,000 from Des Moines Water Works and $554,256.69 City Cost - G.O.
Bonds) with individual estimates for the two streets as follows:
- Druid Hill
Drive from Bell Avenue to Casady Drive (Total Estimate $326,000 with $58,620.13
assessed, $21,000 from Des Moines Water Works for water main construction and
$246,379.87 City Cost - G.O. Bonds)
- E. 35th
Street and Arthur Avenue from Easton Boulevard to E. 34th
Street (Total Estimate $390,000 with $82,123.18
assessed and $307,876.82 City Cost - G.O. Bonds)
Funding Source: 2009-2010 CIP,
Page Street-6, City-wide Paving Program, STR013, being $140,743.31 from Special Assessments against benefited property owners,
$21,000 from Des Moines Water Works and $554,256.69 in G.O. Bonds
ADDITIONAL INFORMATION:
On June 26, 2000, by Roll Call 00-1876, the City Council
adopted a policy for paving residential streets in an effort to pave the
remaining 50 miles of unpaved streets.
This policy specifies that the majority of remaining unpaved streets
will be paved by private contractors with permanent paving over an improved
subbase. Public Works crews will
continue to provide non-assessed residential maintenance paving (formerly known
as “interim paving”) where road use, storm water conditions and available
funding are consistent with this reduced life surfacing. By past Council policy, interim pavement has
been limited to construction of a maximum of 4” of hot mix asphalt over the
existing street surface and does not include construction of curb and gutter or
any storm sewer.
Under said Council policy, the permanent paving is assessed
based upon 50% of the actual pavement costs, 50% of the driveway approach costs
and design and inspection costs limited to 10% of the total construction
cost. This procedure, along with the
existing assessment subsidy program, results in residents typically paying
approximately 25% of total project costs.
Currently, petitions for paving from the following two streets
have been submitted to Council:
- Druid Hill Drive from Bell
Avenue to Casady Drive
- E. 35th Street
and Arthur Avenue from Easton Boulevard to E. 34th Street
Council Communication No. 09-719, which was attached to Roll
Call No. 09-1831, dated October 12, 2009, outlines the procedure to be used to
establish the 2009-10 Paving Program, as follows,
which has been updated to the status and scheduled dates:
- Council authorization to
proceed with preliminary work (Authorized under Roll Call 09-1831).
- Informational
Meeting. Each assessed property
owner will receive a mailing from the City Engineer. The mailing will contain general
information about the street paving procedure and each owner's estimated
assessment, and will invite the property owner to an informational meeting
with Engineering staff, at which time the property owners have the
opportunity to ask questions and provide input to staff on the design. (The mailing with general information
was sent January
14, 2010, which included an invitation to the Informational Meeting,
which is scheduled for February 1, 2010 at 6:30 p.m. in the Council
Chambers).
- Preliminary survey would
be completed, initial design work would begin and preliminary cost
estimates developed. (Preliminary
cost estimates have been completed and are incorporated into the
Preliminary Assessment Schedules, which are presented for Council
consideration on the January 25, 2010 agenda.)
- Resolution of
Necessity. The Resolution of
Necessity will be presented to Council for adoption after the
informational meeting with property owners. (The proposed Resolution of Necessity
will be presented on this agenda for Council to set the date for the
Hearing on the Resolution of Necessity as February 22, 2010 at 5:00 p.m.).
The policy of taking alternate bids for hot mix asphalt or
Portland cement concrete will again be utilized for the non-arterial streets
included in the program.
Recommend that the City Council proceed with the following improvements
and direct staff to take the necessary actions under the Iowa Code special
assessment process for Council consideration, as required by Iowa Code, to
assess a portion of the cost on the following improvements:
·
Street paving 26 feet wide B/B with Portland
Cement Concrete six inches thick with integral curb, or with Hot Mix Asphalt
eight inches thick with Portland Cement Concrete curb and gutter, driveway
approaches, water main, surface restoration and other incidental items,
together with the necessary drainage facilities on Druid Hill Drive from Bell
Avenue to Casady Drive, Activity ID 06-2010-011, Schedule No. 2010-01;
·
Street paving 26 feet wide B/B with Portland
Cement Concrete six inches thick with integral curb, or with Hot Mix Asphalt
eight inches thick with Portland Cement Concrete curb and gutter, driveway
approaches, surface restoration and other incidental items, together with the
necessary drainage facilities on E. 35th Street and Arthur Avenue
from Easton Boulevard to E. 34th Street, Activity ID 06-2010-012,
Schedule No. 2010-02.
PREVIOUS COUNCIL ACTION(S):
Date: October 12, 2009
Roll Call Number: 09-1831
Action: Authorization to proceed on
the 2009-10 Paving Program. (Council Communication No. 09-719) Moved by Mahaffey to
adopt. Motion Carried 7-0.
Date: September 14, 2009
Roll Call Number:
09-1693
Action: Petition
from property owners requesting paving for E. 35th Street from
Easton Boulevard to Arthur Avenue, and Arthur Avenue from E. 34th to
E. 35th Street. Moved by Vlassis to receive, file, and
refer to City Engineer for review and recommendation. Motion Carried 7-0.
Date: September 14, 2009
Roll Call Number:
09-1692
Action: Petition
from property owners protesting proposed sidewalk on Druid Hill Drive from
Casady Drive to Bell Avenue. Moved by Hensley to receive, file, and
refer to City Engineer for review and recommendation. Motion Carried 7-0.
Date: July 13, 2009
Roll Call Number:
09-1189
Action: Authorization to proceed on Druid Hill Drive paving
and sidewalk from Bell Avenue to Casady Drive.
(Council
Communication No. 09-447) Moved
by Kiernan to adopt. Motion Carried 7-0.
Date: June 22, 2009
Roll Call Number:
09-1120
Action: Petitions
from property owners requesting paving and sidewalks on Druid Hill Drive, from
Casady Drive to Bell Avenue. Moved by
Hensley to receive, file, and refer to the City Engineer for review and
recommendation. Motion Carried 6-1. Absent:
Mahaffey
Date: June 26, 2000
Roll Call Number:
00-1876
Action: Approving
Assessment Policy for Residential Street Paving. (Council
Communication No. 00-288) Moved
by McPherson to adopt. Motion Carried 7-0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS:
Council Hearing on
the Resolution of Necessity on February 22, 2010, and if adopted, the normal
Council actions to authorize bids, receive and file bids, designate lowest
bidder and approve contract and bond; also, partial payments to the contractor
and final acceptance of work.
For more
information on this and other agenda items, please call the City Clerk’s Office
at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall,
400 Robert D. Ray Drive. Council agendas
are available to the public at the City Clerk’s Office on Thursday afternoon
preceding Monday’s Council meeting.
Citizens can also request to receive meeting notices and agendas by
email by calling the Clerk’s Office or sending their request via email to
cityclerk@dmgov.org.