Agenda Item No. 7 Roll Call No. 10- Communication
No. 10-042 Submitted
by: City
Engineer |
||||
AGENDA
HEADING:
Designation
of lowest responsive, responsible bidder as Herberger Construction Co., Inc.,
Dean Herberger, President, and approval of contract and bond on Court Avenue
& Water Street Gatewell and River Outlet, $390,387.
SYNOPSIS:
Recommend
Council approval of Herberger Construction Co., Inc.,
Dean Herberger, President, as the lowest responsive, responsible bidder on the
Court Avenue & Water Street Gatewell and River
Outlet, and take the necessary actions as required by Iowa Code to authorize a
contract for construction of the proposed project subject to release of funds
by the Iowa Department of Economic Development on Contract No. 08-DRI-232. This project is the first phase of the Court
Avenue & Water Street Sewer Separation project, which will construct a
separate storm sewer system and storm water pump station to
serve this area. This area of downtown
is currently served by a combined (storm and sanitary) sewer system, resulting
in localized flooding during heavy rain events, especially during high river
levels. The Court Avenue & Water
Street Gatewell and River Outlet will construct the required gatewell at the
levee and the outlet to the river.
Future projects will construct the pump station and the storm sewer
system to convey storm water to the new outlet to the river.
FISCAL
IMPACT:
Amount: $390,387 Construction Contract ($537,790 City
Engineer's Estimate)
Funding
Source: 2009-2010 CIP, Page
Storm-6, Court Avenue/Water Street Sewer Separation, STE081, Being: $390,387 in HUD Disaster funds from the Iowa
Department of Economic Development for 100% of construction costs associated
with the Court Avenue - Water Street Sewer Separation project with a $4,000,000
maximum in Federal Jumpstart Infrastructure Assistance funds.
ADDITIONAL
INFORMATION:
On
·
Contract
Number 08-DRI-032 in the amount not to exceed $4,000,000 for the Court Avenue -
Water Street Sewer Separation Project.
·
Contract
Number 08-DRI-033 in the amount not to exceed $5,000,000 for the Lower Union Sewer Separation Project.
·
Contract
Number 08-DRI-034 in the amount not to exceed $1,200,000 for the 33rd Street Sewer Separation Project.
·
Contract
Number 08-DRI-035 in the amount not to exceed $5,000,000 for the Jackson Basin
Pump Station Project.
Before IDED will send these Contracts for execution by the City, IDED has
required the City to execute and return, IDED’s Notice of Award letter for each
contract, whereby the City accepts the award described, acknowledges that
receipt of the Award is contingent upon satisfaction of all conditions of the
Community Development Block Grant (CDBG) program and execution of the Contract,
and agrees to be bound by the program and Contract requirements.
On
On
Sealed
bids for said improvement were received and filed by the City Council under
said Roll Call No. 09-2320 as submitted by the following bidders:
Herberger
Construction Co., Inc., Indianola, IA
Cramer
and Associates, Inc., Grimes, IA
Jensen
Construction Co., Des Moines, IA
H
& W Contracting LLC, Sioux Falls, SD
Van
Hauen & Associates, Inc., Grimes, IA
The
bids were received and opened at a public meeting presided over by the City
Engineer in the City Council Chambers, 2nd Floor, City Hall, 400 Robert D. Ray
Drive, Des Moines, Iowa at 11:00 a.m. on
On
PREVIOUS
COUNCIL ACTION(S):
Date:
Roll Call Number: 09-2320
Action: On Court Avenue & Water Street Gatewell
and River Outlet: Resolution approving
plans, specifications, form of contract documents, engineer’s estimate, and
receive and file bids. (Council Communication No. 09-880) Moved by Hensley to
adopt. Motion Carried 7-0.
Action: Ordering construction of Court Avenue &
Water Street Gatewell and River Outlet:
Receiving of bids, (12-15-09), and Setting date of hearing,
(12-21-09). (Construction
Estimate - $537,790). (Council
Communication No. 09-823) Moved by Coleman to adopt. Motion Carried 7-0.
Action: Approving and authorizing the execution of CDBG
Disaster Recovery Infrastructure Notice of Award and Grant Contracts with the
Iowa Department of Economic Development for 4 projects: (Council
Communication No. 09-801) Moved by Hensley to adopt.
Motion Carried 4-3.
Action: Approving Professional Services
Agreement with Veenstra & Kimm, Inc. for design and construction phase
services for the Court Avenue-Water Street Sewer Separation Project, not to
exceed $595,712. (Council
Communication No. 08-646) Moved
by Hensley to adopt. Motion Carried 7-0.