Date
|
|
||
|
Agenda
Item No. 8 Roll
Call No. 10- Communication No.
10-045 Submitted by: City Engineer |
||||
AGENDA HEADING:
Approving
and authorizing the execution of Amendment No. 1 to the United States
Department of Agriculture Natural Resources Conservation Service Project
Agreement for the Emergency Watershed Protection Program for 1235 Davis Avenue
Slope Stabilization.
SYNOPSIS:
Recommend approval of Amendment No. 1 to the agreement
between the City of Des Moines and the United States Department of Agriculture
(USDA) Natural Resources Conservation Service (NRCS) for the Emergency
Watershed Protection (EWP) Program for 1235
Davis Avenue Slope Stabilization, extending the completion date from
FISCAL IMPACT:
Amount: $171,943.35 total estimated project cost
Funding Source: 2009-2010
CIP, Page Storm-4, City-wide Storm Water Utility Projects, STE057, various
funding being:
·
$88,350
in Federal funds from the USDA-NRCS EWP Program Funds for 75% of construction
contract costs, not to exceed $88,350, per Agreement No. 69-6114-9-49.
·
$9,424
in Federal funds for design and inspection costs from the USDA-NRCS EWP Program
Funds (maximum 8% of construction contract cots, not to exceed $9,424) per
Agreement No. 69‑6114-9-49.
·
$25,000
in Jump Start Funds from the adjacent property owner, as per existing agreement
with property owners Trelen J. Wilson
and Linda L. Bender.
·
$32,939.35 in private contributions from the
adjacent property owner, as per agreement with the property owners.
·
$16,230
in Storm Water Utility funds from STE057, plus any change orders or overages.
ADDITIONAL INFORMATION:
The USDA-NRCS operates the EWP
program with the stated purpose of undertaking “emergency measures for soil erosion
prevention to safeguard lives and property from floods, drought, and the
products of erosion on any watershed whenever fire, flood, or any other natural
occurrence is causing or has caused a sudden impairment of the watershed.”
During and subsequent to the
heavy rains and flooding in June 2008, severe soil erosion and landslides
occurred near 1235 Davis Avenue. On
On
PREVIOUS COUNCIL ACTION(S):
Date:
Roll Call Number: 09-1710
Action:
On 1235 Davis Avenue Soil
Stabilization: Resolution approving
plans, specifications, form of contract documents, engineer’s estimate and
designating lowest responsible bidder as Hardscape Solutions of Iowa, Inc.,
(Curtis Richey, President), $137,519.35.
(Council Communication No. 09-661). Moved by Hensley to
adopt. Motion Carried 7-0.
Action:
Approving amendment to agreement with Trelen J. Wilson and Linda L. Bender regarding property at
1235 Davis Avenue. (Council
Communication No. 09-601) Moved
by Kiernan to adopt. Motion Carried 7-0.
Action:
Approving and authorizing the execution
of an agreement with Trelen J. Wilson and Linda L.
Bender regarding 1235 Davis Avenue and to acquire necessary property
interests. (Council
Communication No. 09-107) Moved by Hensley to adopt. Motion carried 7-0.
Action:
Authorization to submit grant application to U.S. Department
of Agriculture Emergency Watershed Protection Program for soil erosion prevention
and repair projects related to 2008 heavy rains and flooding. (Council
Communication No. 08-577)
Moved by Hensley to adopt. Motion
Carried 7‑0.
BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS: