Agenda Item No. 8 Roll Call No. 10- Communication
No. 10-125 Submitted
by: Jeb E. Brewer, P.E. City Engineer |
||||
AGENDA
HEADING:
Approving Supplemental Agreement No. 2 to the East Indianola Avenue
Roadway Design, S.E. 14th Street to Army Post Road Professional
Services Agreement with Snyder & Associates, Inc. for design of the
pedestrian underpass and trail connections, not to exceed $33,500.
SYNOPSIS:
Recommend
approval of Supplemental Agreement No. 2 to the Professional Services Agreement
with Snyder & Associates, Inc., David Moeller, President, 2727 S.W. Snyder
Blvd, Ankeny, IA 50023, for a total cost not to exceed $33,500, based on hourly
rates to design the pedestrian underpass and trail connections in Ewing Park.
FISCAL
IMPACT:
Amount: $33,500
Funding Source: 2010-2011 CIP, Page Street-21, East Indianola
Avenue Widening – S.E. 14th to Army Post Road, STR213, $33,500 in G.O. Bonds
ADDITIONAL
INFORMATION:
Supplemental
Agreement No. 2 includes the additional design services needed to design the
pedestrian underpass and trail connections as part of the East Indianola Avenue
Widening project. The pedestrian
underpass and trail connections will be incorporated into the plans being
prepared for Phase 2 of the project.
The
current agreement with Snyder & Associates, Inc. includes design of
East Indianola from SE 14th Street to Army Post Road. At the time this agreement was developed,
funding had not been secured for the pedestrian underpass and trail
connections. Last year the Des Moines
Area Metropolitan Planning Organization approved $200,000 of Surface
Transportation Program Transportation Enhancement funding in Federal FY2013 for
this trail. With the planned widening of
East Indianola, adding the pedestrian underpass to the roadway project is the
most efficient and cost effective way to get the work done.
As part
of the East Indianola Avenue corridor consultant selection process in 2005,
staff received proposals from seven engineering firms. A committee comprised of City staff from the
Engineering Department, Parks Department, and Public Works Department reviewed
these proposals and recommended that Snyder & Associates, Inc. be selected
for this study. A major factor in
recommending Snyder & Associates, Inc. was their extensive past involvement
in projects near or within this corridor.
PREVIOUS
COUNCIL ACTION(S):
Date: August 10, 2009
Roll
Call Number: 09-1499
Action: Approving
Supplemental Agreement No. 1 to the E. Indianola from SE 14th to
Army Post Road Professional Services Agreement with Snyder & Associates,
Inc. to provide construction phase services for the E. Indianola – SE 14th
Street to SE 16th Court, not to exceed $54,004. (Council
Communication No. 09-559) Moved by Meyer to
adopt. Motion Carried 7-0.
Date: October 8, 2007
Roll
Call Number:
07-1994
Action: E. Indianola Avenue Corridor Study, and Professional Services Agreement with Snyder & Associates, Inc. (David Moeller, P.E., President, Ankeny, IA) for the E. Indianola Avenue Roadway Design, $988,908. (Council Communication No. 07-601
) Moved by Meyer to adopt. Motion Carried 7-0.BOARD/COMMISSION
ACTION(S): NONE
ANTICIPATED
ACTIONS AND FUTURE COMMITMENTS: