Agenda Item No.        6A

Roll Call No.               10-

Communication No.   10-131

Submitted by:  Jeb E. Brewer, P.E.,

                          City Engineer

 

 

AGENDA HEADING:

 

Ordering construction of the following:  S.W. 7th Street Bridge over the Raccoon River Rehabilitation - Receiving bids, (3-16-10), and Setting date of hearing, (4-12-10). (Construction Estimate - $1,715,469).

 

 

SYNOPSIS:

 

Recommend the City Council proceed with construction of the improvement and set dates to receive bids and hold a public hearing, as required by Iowa Code, utilizing the method of financing referenced below. The rehabilitation of the S.W. 7th Street Bridge over the Raccoon River was identified as a high priority project on the 2009 City-Wide Bridge and Structure Evaluation.

 

 

FISCAL IMPACT:

 

Amount:  $1,715,469 City Engineer's Estimate

 

Funding Source:  2010-2011 CIP, Page Bridge-15, S.W. Seventh Street Bridge over the Raccoon River, BRV046:  The project is eligible for 80% HBRR funding up to a maximum of $1,000,000 under IDOT Agreement No. 01-09-HBRRU-005, with the remaining $715,469 from G. O. Bonds.

 

 

ADDITIONAL INFORMATION:

 

Due to the condition of this structure, it has become eligible for Federal Highway Bridge Program Funds and the City has an agreement with Iowa Department of Transportation funding 80% of the construction costs up to a maximum of $1,000,000.

 

Recent bridge inspections have determined that this structure, which was originally constructed in 1915 and last rehabilitated in 1968, is showing signs of deterioration and should be rehabilitated.  Work included in the project consists of deck repairs, expansion joint replacement, placement of a high-density portland cement concrete overlay, repair of structural elements including piers, columns, and arches, and repair of curbs, sidewalks, and approach pavement.  Because this will be a major rehabilitation of the existing structure, S.W. 7th Street will be closed during construction.

 

The Engineering Department has prepared plans, specifications, form of contract documents, and City Engineer’s estimate for the construction of the S.W. 7th Street Bridge over the Raccoon River Rehabilitation, 12-2009-002.  The improvement includes concrete removals, structural concrete, reinforcing steel, epoxy coated reinforcing steel, deck overlay, deck repair, steel extrusion joint with neoprene, neoprene gland installation and testing, blast cleaning structural steel, painting structural steel,  removal of sidewalk, sidewalk 6" PCC, electrical circuit, construction survey, pavement markings, temporary concrete barrier rail, traffic control, changeable message sign, mobilization, bearing repair, epoxy crack injection and concrete repairs; all in accordance with the contract documents, including Plan File Nos. 509-119/149 for the S.W. 7th Street Bridge over the Raccoon River in Des Moines, Iowa.

 

The estimated construction cost is $1,715,469.  The proposed plans, specifications, and form of contract documents are available for public inspection in the City Engineer's Office.

 

 

 


PREVIOUS COUNCIL ACTION(S): 

 

Date:  April 20, 2009 

 

Roll Call Number:  09-611

Action:  Shuck-Britson, Inc. for evaluation, design, and construction phase services for the SW 7th Street Bridge over the Raccoon River Rehabilitation, not to exceed $196,733.  Council Communication No.  09-240) Moved by Vlassis to adopt.  Motion Carried 7-0.    

 

Date:  March 9, 2009 

 

Roll Call Number:  09-366

Action:  Approving execution of Iowa Department of Transportation Agreement for S.W. 7th Street over Raccoon River Bridge Rehabilitation.  (Council Communication No.  09-143) Moved by Vlassis to adopt.  Motion Carried 7-0.

 

                                   

BOARD/COMMISSION ACTION(S):  NONE

 

 

ANTICIPATED ACTIONS AND FUTURE COMMITMENTS:

 

Anticipated actions include public hearing, receive and file bids, designate lowest bidder, and approve contract and bond; also partial payments to the contractor and final acceptance of work.

 

 

 

 

For more information on this and other agenda items, please call the City Clerk’s Office at 515-283-4209 or visit the Clerk’s Office on the second floor of City Hall, 400 Robert D. Ray Drive.  Council agendas are available to the public at the City Clerk’s Office on Thursday afternoon preceding Monday’s Council meeting.  Citizens can also request to receive meeting notices and agendas by email by calling the Clerk’s Office or sending their request via email to cityclerk@dmgov.org.